Joyville Shapoorji Housing Private Limited

19 RERA-registered projects in Pune, across 2 localities.

16under construction
3delivered
1past their date
1complaints
1 of the 16 projects this promoter still has under construction is past the completion date on their own filing.

Under construction — 16 projects

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Joyville Celestia Phase 1 Shewalewadi Mar 2028 Jul 2028 Under construction 65% 0
Joyville Celestia Phase 2 Shewalewadi Mar 2028 Jul 2028 Under construction 81% 0
Joyville Celestia Phase 3 Shewalewadi Jun 2028 Oct 2028 Under construction 83% 0
Joyville Celestia Phase 6 Shewalewadi Sep 2029 Jan 2030 Under construction 30% 0
Ews Building - Wing B Shewalewadi Sep 2027 Jan 2028 Under construction 9% 0
Ews Building - Wing A Shewalewadi Mar 2027 Jul 2027 Under construction 6% 0
Vyomora Phase 1 Maan Apr 2031 Aug 2031 Under construction 0% 0
Joyville Hadapsar Annexe Phase 17 Shewalewadi Dec 2027 Apr 2028 Under construction 46% 0
Joyville Celestia Phase 5 Shewalewadi Oct 2028 Feb 2029 Under construction 61% 0
Joyville Hadapsar Annexe Retail Shewalewadi Oct 2027 Feb 2028 Under construction 93% 0
Sensorium, Phase Vii Maan Dec 2026 Apr 2027 Under construction 100% 0
Joyville Hadapsar Annexe Phase 16 Shewalewadi Dec 2026 Apr 2027 Under construction 100% 0
SENSORIUM, Phase VI Maan Sep 2026 Sep 2026 7 days over 100% 0
Joyville Hadapsar Sky-Luxe Shewalewadi Dec 2026 Dec 2026 Under construction 95% 0
Joyville Hadapsar Annexe Phase 20 Shewalewadi Dec 2026 Dec 2026 Under construction 93% 0
Joyville Hadapsar Annexe Phase 18 Shewalewadi Dec 2026 Dec 2026 Under construction 92% 0
Advertisement
Track record Delivered — 3 projects Handed over; late deliveries are the best guide to the next deadline.

Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch.

ProjectLocalityPromised Handed over Late by SoldComplaints
Sensorium, Phase I Maan May 2025 May 2025 On time 100% 1
Joyville Hadapsar Annexe Phase 14 Shewalewadi Dec 2025 Dec 2025 On time 100% 0
Ews Building - Wing D Shewalewadi Dec 2025 Dec 2025 On time 0% 0

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Joyville Shapoorji Housing Private Limited's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.