13 RERA-registered projects in Pune, across 6 localities.
Under construction — 12 projects
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| The Collection - W2 and W7 | Viman Nagar | Sep 2026 | Sep 2026 | Under construction | 86% | 0 |
| The Collection Premium | Viman Nagar | Dec 2026 | Dec 2026 | Under construction | 90% | 0 |
| August Towers Ph 1 | Viman Nagar | Dec 2028 | Dec 2028 | Under construction | 88% | 1 |
| Hues Of Sky | Ghorpadi | Dec 2029 | Dec 2029 | Under construction | 46% | 0 |
| Boulevard Tower A2 | Ghorpadi | Dec 2026 | Dec 2026 | Under construction | 54% | 0 |
| The Collection - W5 And W6 | Viman Nagar | Dec 2029 | Dec 2029 | Under construction | 43% | 0 |
| Bramhacorp Townhouse A | Balewadi | Dec 2027 | Dec 2027 | Under construction | 90% | 0 |
| Boulevard Wing B 1 | Ghorpadi | Dec 2028 | Dec 2028 | Under construction | 23% | 0 |
| Sky Suites By Bramhacorp | Ghorpadi | Dec 2029 | Dec 2029 | Under construction | 29% | 0 |
| August Towers Ph 2 | Vadgaon Sheri | Dec 2031 | Dec 2031 | New launch | 0% | 0 |
| Harmony Heights | Viman Nagar | May 2027 | May 2027 | New launch | 0% | 0 |
| Kalpana Co Op Hsg Soc Ltd - Phase 1 | Yerawada | Dec 2031 | Dec 2031 | New launch | 0% | 0 |
Track record Delivered — 1 project Handed over; late deliveries are the best guide to the next deadline.
Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch.
| Project | Locality | Promised | Handed over | Late by | Sold | Complaints |
|---|---|---|---|---|---|---|
| Bramhacorp Townhouse A1 | Baner | Dec 2027 | Dec 2027 | On time | 85% | 0 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Bramhacorp Limited's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.