In short

The Central Park Phase-2 in Manchar is MahaRERA-registered (PR1260002602031) and still under construction, with possession filed for December 2033. No sales are registered in this project yet. Units the same size elsewhere in Manchar have registered at ₹4,806 per sq ft of carpet — the neighbourhood, not this building. None of the units are filed as sold yet. Supreme Infra is the promoter.

Stock image, not a photograph of The Central Park Phase-2 Stock image
Where
Manchar
pincode 410503
Nearby at
₹4,806
per sq ft, same sizes in Manchar
Available
1, 2 BHK
51 left · 372–547 sq ft
Possession
Dec 2033
as filed with MahaRERA
A stock photograph, not The Central Park Phase-2. We have no picture of this site yet.
Plot Demarcation

Land & Survey Location

Official parcel address and geographic coordinates as declared to MahaRERA.

Jurisdiction Manchar (CT) · Ambegaon

Manchar, Pune, 410503

Village Manchar (CT)
Taluka Ambegaon
Pincode 410503
Promoter Pin Coordinates 18.990927, 73.953227

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

Flat sizes on file

All 84 flats are filed unit by unit with the authority, the highest on floor 7. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

Configuration Mix & Volume Proportional share of project density
84 Total Licenced Units
Residential Typology • 33.3% of tower

1 BHK Residences

18 Available 28 registered total
Estimated Market Window ₹17.9 lakh – ₹18.6 lakh
Locality Benchmark ₹4,806 / sq ft
Carpet Variations as Filed Span: 372 to 387 sq ft
372 sq ft 34.58 sq m 14 units
387 sq ft 35.91 sq m 14 units
Govt ASR Base: ₹14 lakh – ₹15.2 lakh 18 of 28 available
Dominant Typology • 66.7% of tower

2 BHK Residences

33 Available 56 registered total
Estimated Market Window ₹26.3 lakh
Locality Benchmark ₹4,806 / sq ft
Carpet Variations as Filed Span: 547 sq ft
547 sq ft 50.85 sq m 56 units
Govt ASR Base: ₹19.2 lakh – ₹20.2 lakh 33 of 56 available

Carpet Area vs. Loading Factor Arithmetic

How statutory carpet translates to standard Pune market quoted areas (+20% Built-up, +40% Super Built-up)

Unit Configuration Statutory RERA Carpet (Actual) Approx Built-up (+20%) Super Built-up (+40% Loading) Available Inventory
1 BHK 372 – 387 sq ft (34.58 – 35.91 sq m) ~446 – 464 sq ft ~521 – 542 sq ft 18 left of 28
2 BHK 547 sq ft (50.85 sq m) ~656 sq ft ~766 sq ft 33 left of 56
Units sold

0 / 84

Pre-launch / early phase

0% absorption rate

Visual area guide See what the filed sizes feel like 2 generic footprints scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

1 BHK 28 flats · 18 available

372 sq ft carpet as drawn, from 372–387 sq ft filed in this configuration

Carpet, filed
372 sq ft
Built-up
about 446 sq ft
Super built-up
about 521 sq ft
Every room in this flat

Living and dining about 140 sq ft, Master bedroom about 93 sq ft, Kitchen about 56 sq ft, Bath about 33 sq ft, Balcony about 33 sq ft, Passage about 19 sq ft.

2 BHK 56 flats · 33 available

547 sq ft carpet as drawn

Carpet, filed
547 sq ft
Built-up
about 656 sq ft
Super built-up
about 766 sq ft
Every room in this flat

Living and dining about 159 sq ft, Master bedroom about 106 sq ft, Second bedroom about 85 sq ft, Kitchen about 64 sq ft, Bath about 37 sq ft, Balcony about 37 sq ft, Second bath about 32 sq ft, Passage about 27 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What flats like these cost nearby

No sale has been registered at The Central Park Phase-2 yet. The promoter has filed no agreement values, so nothing below is this project's own price.

Independent Market Intelligence

Registered Agreement Rates in Manchar

Based on 12 government-stamped sale deeds registered for identical carpet bands across nearby developments.

1 BHK 372–387 sq ft
₹4,806 / sq ft

12 registered sale agreements across 2 nearby developments.

Estimated Unit Market Window ₹17.9 lakh – ₹18.6 lakh
Middle Half (IQR) ₹4,600 – ₹5,188 / sq ft
25th percentile: ₹4,600 75th percentile: ₹5,188

2 BHK is also on sale here, and Manchar has not registered enough sales of that to quote a rate for it.

Each rate is what buyers contracted to pay for the same configuration in Manchar, over the carpet area on the same filing. Floor and facing move a rate, and a project new on the register can open above or below what its neighbours sold at two years ago, so the last column is arithmetic rather than a quote. See every rate registered in Manchar.

The government's valuation of the unsold flats

On sale here Carpet Valued at no less than
1 BHK 18 unsold 372–387 sq ft ₹14 lakh–₹15.2 lakh ₹3,756/sq ft
2 BHK 33 unsold 547 sq ft ₹19.2 lakh–₹20.2 lakh ₹3,516/sq ft

This is the Annual Statement of Rates value the promoter filed against each unsold flat — the state's valuation, not an asking price and not a discount. Stamp duty is charged on whichever is higher, this or the agreement value, so nothing here can be registered below it. Read it as the floor under the price you will be quoted, which in most Pune localities sits well above it.

Filing Compliance

Timeline audit & delivery schedule

Possession milestones tracked directly against original MahaRERA declarations.

Filing State On Scheduled Baseline
Original Baseline
Dec 2033
Declared at registration
Current Statutory Date
Due
Dec 2033
Identical to original baseline

Stable delivery projection

Stable project schedule. Zero slippage or revision requests reported since initial registration. Construction is recorded against the original baseline date.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

Survey No. 120/1A Part, 120/2A, 120/2B, 120/12A, 120/12B is the plot this project is built on, as filed
Revenue village Manchar (CT) · shown on this site as Manchar
TalukaAmbegaon
Street, as filed Pimpalgaon Road
Bounded north by Manchar Pimpalgaon road
Bounded east by Survey No.120/3, 120/4, 120/5
Bounded south by Survey No.119
Bounded west by Survey No.121

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerSupreme Infra
Registered officeC2-201, Chitra Building Nakshatra Residency, Pune Nashik Highway, Manchar, Ghule Mala, Pune 410503

Professionals named on the filing

Architect Pratik Patole CA/015/67340
Engineer Avadhut Tukaram Shete 724/2022/23
Chartered Accountant Sunil Nimbalkar & Associates 197121

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

15 September 2026 is when an advocate last certified the title to this land
Title report Legal title report.pdf 15 September 2026
Promoter's declaration, Form B Form B (Affidavit cum Declaration)_Developer OK.pdf 15 September 2026
Annexure A declaration ANNEXURE A_as per Order No 50 OK.pdf 16 September 2026

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberPR1260002602031
Promoter Supreme Infra
Project typeResidential / Group Housing · Building development
LocalityManchar — Ambegaon taluka, pincode 410503
Applied on16 September 2026
Registered on24 September 2026
Completion, as first filed31 December 2033
Due31 December 2033
Units declared84
Units sold None sold yet, all 84 on the market
Complaints0 on record with MahaRERA
Certificate on file Original registration certificate, issued 24 September 2026
Application referenceACK09092603138
Current statusActive
Record last changed 24 September 2026 · 29 days ago

Nothing has sold yet. The promoter's quarterly progress report says none of the 84 flats are gone, and the unit-by-unit list they file separately says the same: all 84 still unsold. On a project this new that is normal rather than a warning, and it means every carpet area filed here is still available. Either way, this is only as current as the last change to the record, 24 September 2026.

Public Due Diligence

Common questions & statutory checks

Direct answers to questions buyers ask, verified strictly against the MahaRERA filing and registered deed records.

Verified Checks 7 Direct Answers
Is The Central Park Phase-2 registered with MahaRERA?
Yes. It is registered as PR1260002602031, filed on 24 September 2026, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is The Central Park Phase-2 due to be handed over?
The promoter has told MahaRERA December 2033. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has The Central Park Phase-2 been delayed?
No. December 2033 is the date first filed with the authority and it has not moved since.
What does a flat in The Central Park Phase-2 cost?
Nothing has been registered in this project yet, so it has no price of its own. Units the same size elsewhere in Manchar have registered at ₹4,806 per square foot of carpet — the neighbourhood, not this building.
How many flats are left in The Central Park Phase-2?
51 of 84 were still unsold at the promoter's last filing, in 1, 2 BHK, from 372–547 sq ft of carpet.
Are there complaints against The Central Park Phase-2?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building The Central Park Phase-2?
Supreme Infra, as the promoter named on the registration.

Verify Government Filings Yourself

This dossier restates public records as filed on 23 October 2026. The authority's own registry page for PR1260002602031 carries sanctioned layout drawings, escrow accounts, quarterly progress filings, and title documents.

MahaRERA requires a CAPTCHA first. That is their verification gate, not a broken link.

Other projects in Manchar

Stock image, not a photograph of Yamunai Residency Stock image
Locality median
₹4,934
On offer
Row Houses
Under construction

Yamunai Residency

Shivshri Developers · Manchar

13 sold
Slipped 4 months
Due
May 2028
Units
15
Carpet
933–1,082
Typical flat
~₹53.4 lakh
P52100056046
Stock image, not a photograph of Anandi Malhar Stock image
Registered here
₹4,236
On offer
1, 2 BHK + row houses
Under construction

Anandi Malhar

Reliable Constructions · Manchar

13 sold
Slipped 4 months
Due
Apr 2028
Units
38
Carpet
309–826
Sold at
₹35 lakh
PR1260002501174