Jitendra Heritage - E 2 Building - Phase - 1

Pashan, Pune · Residential / Group Housing by Jitendra Constructions

Official record Updated from the register 30 October 2026. Anything filed since then is not here yet.

In short

Jitendra Heritage - E 2 Building - Phase - 1 in Pashan is MahaRERA-registered (P52100009234) and still under construction, with possession filed for December 2030. No sales are registered in this project yet. Across Pashan, buyers have been registering around ₹13,003 per sq ft of carpet (1050 sales in the locality) — the area median, not this building. About 100% of the 1 units are sold. Jitendra Constructions is the promoter.

Stock image, not a photograph of Jitendra Heritage - E 2 Building - Phase - 1 Stock image
Where
Pashan
pincode 411045
Pashan at
₹13,003
per sq ft across the locality, not this project
Available
None left
every flat filed as sold or held
Now due
Dec 2030
7.3 years later than first promised
A stock photograph, not Jitendra Heritage - E 2 Building - Phase - 1. We have no picture of this site yet.
Plot Demarcation

Land & Survey Location

Official parcel address and geographic coordinates as declared to MahaRERA.

Jurisdiction Pashan · Haveli

Pashan, PMC, Pune, 411045

Village Pashan
Taluka Haveli
Pincode 411045

The promoter filed a coordinate that falls outside Pune district, so it is not used here. The link above searches Maps by name and locality instead.

Flat sizes on file

All 1 flats are filed unit by unit with the authority, the highest on floor 1. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

Configuration Mix & Volume Proportional share of project density
1 Total Licenced Units
Residential Typology • 100.0% of tower

1 BHK Residences

0 Available 1 registered total
Estimated Market Window ₹99.7 lakh
Locality Benchmark ₹13,003 / sq ft
Carpet Variations as Filed Span: 767 sq ft
767 sq ft 71.25 sq m 1 unit
None available

Carpet Area vs. Loading Factor Arithmetic

How statutory carpet translates to standard Pune market quoted areas (+20% Built-up, +40% Super Built-up)

Unit Configuration Statutory RERA Carpet (Actual) Approx Built-up (+20%) Super Built-up (+40% Loading) Available Inventory
1 BHK 767 sq ft (71.25 sq m) ~920 sq ft ~1074 sq ft 0 left of 1
Units sold

1 / 1

Nearly sold out

100% absorption rate

Visual area guide See what the filed sizes feel like 1 generic footprint scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

1 BHK 1 flat · none available

767 sq ft carpet as drawn

Carpet, filed
767 sq ft
Built-up
about 920 sq ft
Super built-up
about 1,074 sq ft
Every room in this flat

Living and dining about 288 sq ft, Master bedroom about 192 sq ft, Kitchen about 115 sq ft, Bath about 67 sq ft, Balcony about 67 sq ft, Passage about 38 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What flats like these cost nearby

No sale has been registered at Jitendra Heritage - E 2 Building - Phase - 1 yet. 1 agreement has been filed, which is too few to divide into a rate anyone should act on.

Median across Pashan ₹13,003 per sq ft of carpet, from 1,050 registered sales
The middle half of them ₹11,142 to ₹14,668 per sq ft
Carpet sizes filed here767 sq ft
Still available 0 flats

This is Pashan as a whole and not a rate for Jitendra Heritage - E 2 Building - Phase - 1, and it is pooled across every configuration the locality has registered — studios and four-bedroom flats included — because Pashan has not filed enough sales of any single configuration on sale here to quote one separately. Treat it as the order of magnitude for the area rather than a figure to negotiate against. See the full distribution for Pashan.

Filing Compliance

Timeline audit & delivery schedule

Possession milestones tracked directly against original MahaRERA declarations.

Filing State Revised (+7.3 years)
Original Baseline
Aug 2023
Declared at registration
Current Statutory Date
Due
Dec 2030
7.3 years later than filed

Revised delivery projection

The completion date has moved from August 2023 to December 2030, 7.3 years later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

Survey No 5/4A, 4B, 5, 5/7 is the plot this project is built on, as filed
Revenue village Pashan
TalukaHaveli
Bounded north by By S no 5 1 and 5 2 and beyond that gaothan
Bounded east by By Land Of T R Nihman
Bounded south by By S No 6 Sutarwadi Pashan
Bounded west by BY P M C Road

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerJitendra Constructions
Registered officeCts No1194/6, Jitendra Villa, Off Ghole Road, Behind Icici, Shivajinagar, Pune 411005

Professionals named on the filing

Engineer Nikhil Shivaji Karande

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

28 July 2017 is when an advocate last certified the title to this land
Title report Search Title.pdf 28 July 2017
Promoter's declaration, Form B Form B new.pdf 30 August 2017 1 older version on file

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100009234
Promoter Jitendra Constructions
Project typeResidential / Group Housing · Building development
LocalityPashan — Haveli taluka, pincode 411045
Applied on29 July 2017
Registered on22 August 2017
Completion, as first filed28 August 2023
Due31 December 2030 7.3 years later
Units declared1
Units sold Sold, the only flat here
Complaints0 on record with MahaRERA
Certificate on file Original registration certificate, issued 09 September 2021
Application referenceREA52100011104
Current statusActive
Record last changed 01 December 2023 · over 2 years ago 2 years untouched

Where the sold count comes from, and whether it holds up. 1 of 1 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 1 flats and reaches the same answer — 1 sold, every one with money recorded as received against a named flat, and 0 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 01 December 2023.

MahaRERA has not recorded a change to this project's record in 2 years, while still listing it as under construction. That date moves on status changes and system updates as well as on anything the promoter files, so it is not proof the site is idle — but on a project still being sold, it is worth asking the promoter what has been filed since.

Public Due Diligence

Common questions & statutory checks

Direct answers to questions buyers ask, verified strictly against the MahaRERA filing and registered deed records.

Verified Checks 7 Direct Answers
Is Jitendra Heritage - E 2 Building - Phase - 1 registered with MahaRERA?
Yes. It is registered as P52100009234, filed on 22 August 2017, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Jitendra Heritage - E 2 Building - Phase - 1 due to be handed over?
The promoter has told MahaRERA December 2030. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Jitendra Heritage - E 2 Building - Phase - 1 been delayed?
Yes. The first date filed was August 2023. It now stands at December 2030, 7.3 years later.
What does a flat in Jitendra Heritage - E 2 Building - Phase - 1 cost?
Nothing has been registered in this project yet, so it has no price of its own. Across Pashan the median registered rate is ₹13,003 per square foot of carpet, which is the area rather than this building.
How many flats are left in Jitendra Heritage - E 2 Building - Phase - 1?
None. All 1 are filed as sold or booked.
Are there complaints against Jitendra Heritage - E 2 Building - Phase - 1?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Jitendra Heritage - E 2 Building - Phase - 1?
Jitendra Constructions, as the promoter named on the registration.

Verify Government Filings Yourself

This dossier restates public records as filed on 30 October 2026. The authority's own registry page for P52100009234 carries sanctioned layout drawings, escrow accounts, quarterly progress filings, and title documents.

MahaRERA requires a CAPTCHA first. That is their verification gate, not a broken link.

Other projects in Pashan

Stock image, not a photograph of Opulence Towers Stock image
Valued from
₹15,622
On offer
Offices + showroom
Under construction

Opulence Towers

Nabar Associates · Pashan

5 sold
Slipped 2.3 years
Due
Apr 2030
Units
21
Carpet
555–1,331
Typical unit
~₹1.9 crore
P52100052161