Little Earth, Kiwale - Building D1

Kiwale, Pune · Residential / Group Housing by Kolte-Patil Developers Limited

Official record Updated from the register 24 September 2026. Anything filed since then is not here yet.

In short

Little Earth, Kiwale - Building D1 in Kiwale is MahaRERA-registered (P52100078759) and still under construction, with possession filed for October 2029. Buyers have already registered 81 sales here at a median ₹8,913 per sq ft of carpet — not an asking price. About 48% of the 170 units are sold. Kolte-Patil Developers Limited is the promoter.

Stock image, not a photograph of Little Earth, Kiwale - Building D1 Stock image
Where
Kiwale
pincode 412101
Sold here at
₹8,913
per sq ft, 81 registered sales
Available
2, 3 BHK
89 left · 611–876 sq ft
Now due
Oct 2029
4 months later than first promised
A stock photograph, not Little Earth, Kiwale - Building D1. We have no picture of this site yet.

Where this is

Kiwale, PCMC, Pune, 412101

Village
Kiwale
Taluka
Haveli
Pincode
412101

No coordinate was filed for this project, so this searches Maps by name and locality rather than dropping a pin we cannot vouch for.

Flat sizes on file

All 170 flats are filed unit by unit with the authority, the highest on floor 22. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

2 BHK 85 units · 24 available

41 units 611 sq ft 56.75 sq m as filed
44 units 641 sq ft 59.51 sq m as filed

3 BHK 85 units · 65 available

42 units 787 sq ft 73.15 sq m as filed
22 units 874 sq ft 81.23 sq m as filed
21 units 876 sq ft 81.42 sq m as filed
Units sold

81 / 170

Selling steadily

48% absorption rate

Visual area guide See what the filed sizes feel like 2 generic footprints scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

2 BHK 85 flats · 24 available

641 sq ft carpet as drawn, from 611–641 sq ft filed in this configuration

Carpet, filed
641 sq ft
Built-up
about 769 sq ft
Super built-up
about 897 sq ft
Every room in this flat

Living and dining about 187 sq ft, Master bedroom about 124 sq ft, Second bedroom about 100 sq ft, Kitchen about 75 sq ft, Bath about 44 sq ft, Balcony about 44 sq ft, Second bath about 37 sq ft, Passage about 31 sq ft.

3 BHK 85 flats · 65 available

787 sq ft carpet as drawn, from 787–876 sq ft filed in this configuration

Carpet, filed
787 sq ft
Built-up
about 944 sq ft
Super built-up
about 1,102 sq ft
Every room in this flat

Living and dining about 194 sq ft, Master bedroom about 129 sq ft, Second bedroom about 103 sq ft, Third bedroom about 84 sq ft, Kitchen about 77 sq ft, Bath about 45 sq ft, Balcony about 45 sq ft, Second bath about 39 sq ft, Passage about 39 sq ft, Third bath about 32 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹8,913 per sq ft of carpet, median of 81 registered sales
Range across those sales ₹8,509 to ₹9,460 per sq ft
Sold and booked 0 sold, 81 booked
Still available 89 flats, 611–876 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold flats carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

Timeline audit

Original proposed Jun 2029
Current status Due Oct 2029

Revised projection

The completion date has moved from June 2029 to October 2029, 4 months later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

19/1 to 7 + 9/1 is the plot this project is built on, as filed
Revenue village Kiwale
TalukaHaveli
Street, as filed Kiwale
Bounded north by Open Space Proposed Road
Bounded east by Open Parking Bldg D2 S No 20 P
Bounded south by Projects Land with Podium S No 19 P
Bounded west by 18 M DP Road Mamurdi Village Boundary

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerKolte-Patil Developers Limited
Registered office7th Floor And 8th Floor, Cts No. 14 (P), City Bay, Dhole Patil Road, 17 Boat Club Road, Pune 411001

Title and ownership papers

7 October 2024 is when an advocate last certified the title to this land
Title report RERA Title Report-KPDL.pdf 7 October 2024
Promoter's declaration, Form B Affidavit-Form B- Promoter- Little Earth, Kiwale Bldg D1.pdf 7 October 2024

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100078759
Promoter Kolte-Patil Developers Limited
Project typeResidential / Group Housing · Building development
LocalityKiwale — Haveli taluka, pincode 412101
Applied on14 November 2024
Registered on10 January 2025
Completion, as first filed30 June 2029
Due30 October 2029 4 months later
Units declared170
Units sold 81 of 170 sold (48%), 89 still unsold
Complaints0 on record with MahaRERA
Certificate on file Original registration certificate, issued 14 January 2025
Application referenceREA52100165628
Current statusActive
Record last changed 10 January 2025 · 20 months ago

Where the sold count comes from, and whether it holds up. 81 of 170 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 170 flats and reaches the same answer — 0 sold, 81 booked with a price agreed but nothing received yet, and 89 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 10 January 2025.

Common questions

Is Little Earth, Kiwale - Building D1 registered with MahaRERA?
Yes. It is registered as P52100078759, filed on 10 January 2025, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Little Earth, Kiwale - Building D1 due to be handed over?
The promoter has told MahaRERA October 2029. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Little Earth, Kiwale - Building D1 been delayed?
Yes. The first date filed was June 2029. It now stands at October 2029, 4 months later.
What did buyers actually pay in Little Earth, Kiwale - Building D1?
A median of ₹8,913 per square foot of carpet, across 81 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many flats are left in Little Earth, Kiwale - Building D1?
89 of 170 were still unsold at the promoter's last filing, in 2, 3 BHK, from 611–876 sq ft of carpet.
Are there complaints against Little Earth, Kiwale - Building D1?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Little Earth, Kiwale - Building D1?
Kolte-Patil Developers Limited, as the promoter named on the registration.

Check this yourself

This page restates one public record as we read it on 24 September 2026. The authority's own page for P52100078759 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.

MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.