Z Zomefy

RERA registered P52100028092 Active

Aster Park

Jambe, Pune · Others by Wakadkar Associate

Official record Updated from the register 12 September 2026. Anything filed since then is not here yet.

In short

Aster Park in Jambe is MahaRERA-registered (P52100028092) and still under construction, with possession filed for December 2028. Buyers have already registered 32 sales here at a median ₹5,735 per sq ft of carpet — not an asking price. About 40% of the 81 units are sold. Wakadkar Associate is the promoter.

Stock image, not a photograph of Aster Park Stock image
Where
Jambe
pincode 411033
Sold here at
₹5,735
per sq ft, 32 registered sales
Available
1 BHK, 2 BHK, Shops
49 left · 172–732 sq ft
Now due
Dec 2028
4 years later than first promised
A stock photograph, not Aster Park. We have no picture of this site yet.

Where this is

Jambe, PMRDA, Pune, 411033

Village
Jambe
Taluka
Mulshi
Pincode
411033

No coordinate was filed for this project, so this searches Maps by name and locality rather than dropping a pin we cannot vouch for.

Unit sizes on file

All 81 units are filed unit by unit with the authority, the highest on floor 8. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

1 BHK 51 units · 31 available

8 units 406 sq ft 37.69 sq m as filed
9 units 475 sq ft 44.16 sq m as filed
9 units 478 sq ft 44.44 sq m as filed
9 units 480 sq ft 44.62 sq m as filed
10 units 482 sq ft 44.78–44.82 sq m as filed
6 units 483 sq ft 44.83 sq m as filed

2 BHK 20 units · 8 available

1 unit 483 sq ft 44.83 sq m as filed
15 units 727 sq ft 67.56 sq m as filed
4 units 732 sq ft 68.03 sq m as filed

Shops 10 units · all available

2 units 172 sq ft 16.01 sq m as filed
8 units 217 sq ft 20.13 sq m as filed
Units sold

32 / 81

Selling steadily

40% absorption rate

Visual area guide See what the filed sizes feel like 2 generic footprints scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a unit that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that unit, and each unit to its size against the largest one drawn below.

1 BHK 51 units · 31 available

482 sq ft carpet as drawn, from 406–483 sq ft filed in this configuration

Carpet, filed
482 sq ft
Built-up
about 578 sq ft
Super built-up
about 675 sq ft
Every room in this unit

Living and dining about 181 sq ft, Master bedroom about 120 sq ft, Kitchen about 72 sq ft, Bath about 42 sq ft, Balcony about 42 sq ft, Passage about 24 sq ft.

2 BHK 20 units · 8 available

727 sq ft carpet as drawn, from 483–732 sq ft filed in this configuration

Carpet, filed
727 sq ft
Built-up
about 872 sq ft
Super built-up
about 1,018 sq ft
Every room in this unit

Living and dining about 212 sq ft, Master bedroom about 141 sq ft, Second bedroom about 113 sq ft, Kitchen about 85 sq ft, Bath about 49 sq ft, Balcony about 49 sq ft, Second bath about 42 sq ft, Passage about 35 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹5,735 per sq ft of carpet, median of 32 registered sales
Range across those sales ₹3,697 to ₹9,315 per sq ft
Sold and booked 32 sold, 0 booked
Still available 49 units, 172–732 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold units carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

Timeline audit

Original proposed Dec 2024
Current status Due Dec 2028

Revised projection

The completion date has moved from December 2024 to December 2028, 4 years later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

SURVEY NO 144 P is the plot this project is built on, as filed
Revenue village Jambe
TalukaMulshi
Street, as filed SURVEY NO 144 (P)
Bounded north by S NO 144 MARUTI GAIKWAD PROPERTY
Bounded east by 18 MTR ROAD
Bounded south by S NO 144 WAKADKAR ASSOCIATES PROPERTY
Bounded west by S NO 144

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerWakadkar Associate
Registered officeSr.No.130/2/3, Flat No.103, Flat No 103, Nandan Astra, Wakad, Behind Sanket Hotel, Bhumkar Chowk, Pune 411057

Professionals named on the filing

Architect Cs Architects
Engineer Suyesh Waghole
Chartered Accountant Lalit Ashok Pawar 166981
Chartered Accountant Swapnil Prakash Bagul

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

8 December 2020 is when an advocate last certified the title to this land
Title report Search report.pdf 8 December 2020
Promoter's declaration, Form B Form B.pdf 19 November 2020

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100028092
Promoter Wakadkar Associate
Project typeOthers · Building development
LocalityJambe — Mulshi taluka, pincode 411033
Applied on23 January 2021
Registered on31 January 2021
Completion, as first filed31 December 2024
Due31 December 2028 4 years later
Units declared81
Units sold 32 of 81 sold (40%), 49 still unsold
Complaints0 on record with MahaRERA
Certificate on file Extension certificate, issued 12 August 2026
Application referenceREA52100084091
Current statusActive
Record last changed 12 August 2026 · 33 days ago

Where the sold count comes from, and whether it holds up. 32 of 81 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 81 units and reaches the same answer — 32 sold, 31 of them with money recorded as received against a named unit, and 49 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 12 August 2026.

Common questions

Is Aster Park registered with MahaRERA?
Yes. It is registered as P52100028092, filed on 31 January 2021, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Aster Park due to be handed over?
The promoter has told MahaRERA December 2028. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Aster Park been delayed?
Yes. The first date filed was December 2024. It now stands at December 2028, 4 years later.
What did buyers actually pay in Aster Park?
A median of ₹5,735 per square foot of carpet, across 32 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many units are left in Aster Park?
49 of 81 were still unsold at the promoter's last filing, in 1, 2 BHK + shops, from 172–732 sq ft of carpet.
Are there complaints against Aster Park?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Aster Park?
Wakadkar Associate, as the promoter named on the registration.

Check this yourself

This page restates one public record as we read it on 12 September 2026. The authority's own page for P52100028092 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.

MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.