Z Zomefy

RERA registered PR1261012600728 Active

Shankeshwar Kingsland Phase 1

Hinjewadi, Pune · Residential / Group Housing by Shankeshwar Homes Pvt Ltd

Official record Updated from the register 23 September 2026. Anything filed since then is not here yet.

In short

Shankeshwar Kingsland Phase 1 in Hinjewadi is MahaRERA-registered (PR1261012600728) and still under construction, with possession filed for April 2033. No sales are registered in this project yet. Units the same size elsewhere in Hinjewadi have registered at ₹11,089–12,349 per sq ft of carpet — the neighbourhood, not this building. None of the units are filed as sold yet. Shankeshwar Homes Pvt Ltd is the promoter.

Stock image, not a photograph of Shankeshwar Kingsland Phase 1 Stock image
Where
Hinjewadi
pincode 411057
Nearby at
₹11,089–12,349
per sq ft, same sizes in Hinjewadi
Available
2, 3 BHK
43 left · 640–1,151 sq ft
Now due
Apr 2033
4 months later than first promised
A stock photograph, not Shankeshwar Kingsland Phase 1. We have no picture of this site yet.

Where this is

Hinjewadi, PMRDA, Pune, 411057

Street map of Hinjewadi centred on the coordinate filed for Shankeshwar Kingsland Phase 1, about 1.4 km across.
Streets within about 700 m of the pin the promoter filed. Map data © OpenStreetMap contributors.
Village
Hinjavadi (CT)
Taluka
Mulshi
Pincode
411057
Coordinates
18.592450, 73.746059

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

Flat sizes on file

All 164 flats are filed unit by unit with the authority, the highest on floor 11. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

2 BHK 99 units · 18 available

65 units 640 sq ft 59.44 sq m as filed
2 units 786 sq ft 73.06 sq m as filed
29 units 787 sq ft 73.12 sq m as filed
3 units 894 sq ft 83.03 sq m as filed

3 BHK 65 units · 25 available

3 units 963 sq ft 89.43 sq m as filed
33 units 1035 sq ft 96.17 sq m as filed
29 units 1151 sq ft 106.89 sq m as filed
Units sold

0 / 164

Pre-launch / early phase

0% absorption rate

Visual area guide See what the filed sizes feel like 2 generic footprints scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

2 BHK 99 flats · 18 available

640 sq ft carpet as drawn, from 640–894 sq ft filed in this configuration

Carpet, filed
640 sq ft
Built-up
about 768 sq ft
Super built-up
about 896 sq ft
Every room in this flat

Living and dining about 186 sq ft, Master bedroom about 124 sq ft, Second bedroom about 99 sq ft, Kitchen about 75 sq ft, Bath about 43 sq ft, Balcony about 43 sq ft, Second bath about 37 sq ft, Passage about 31 sq ft.

3 BHK 65 flats · 25 available

1,035 sq ft carpet as drawn, from 963–1,151 sq ft filed in this configuration

Carpet, filed
1,035 sq ft
Built-up
about 1,242 sq ft
Super built-up
about 1,449 sq ft
Every room in this flat

Living and dining about 255 sq ft, Master bedroom about 170 sq ft, Second bedroom about 136 sq ft, Third bedroom about 110 sq ft, Kitchen about 102 sq ft, Bath about 59 sq ft, Balcony about 59 sq ft, Second bath about 51 sq ft, Passage about 51 sq ft, Third bath about 42 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What flats like these cost nearby

No sale has been registered at Shankeshwar Kingsland Phase 1 yet. The promoter has filed no agreement values, so nothing below is this project's own price.

₹11,089–12,349 per sq ft of carpet, median of 8,140 registered sales of the same configurations in Hinjewadi
On sale here Registered in Hinjewadi Which for this size is
2 BHK 640–894 sq ft ₹11,089/sq ft 5197 sales, 30 projects ₹71 lakh–₹99.1 lakh middle half ₹9,236–12,468/sq ft
3 BHK 963–1,151 sq ft ₹12,349/sq ft 2943 sales, 29 projects ₹1.2 crore–₹1.4 crore middle half ₹10,671–13,271/sq ft

Each rate is what buyers contracted to pay for the same configuration in Hinjewadi, over the carpet area on the same filing. Floor and facing move a rate, and a project new on the register can open above or below what its neighbours sold at two years ago, so the last column is arithmetic rather than a quote. See every rate registered in Hinjewadi.

The government's valuation of the unsold flats

On sale here Carpet Valued at no less than
2 BHK 18 unsold 640–894 sq ft ₹31.2 lakh–₹45 lakh ₹4,815/sq ft
3 BHK 25 unsold 963–1,151 sq ft ₹45 lakh–₹51.1 lakh ₹4,464/sq ft

This is the Annual Statement of Rates value the promoter filed against each unsold flat — the state's valuation, not an asking price and not a discount. Stamp duty is charged on whichever is higher, this or the agreement value, so nothing here can be registered below it. Read it as the floor under the price you will be quoted, which in most Pune localities sits well above it.

Timeline audit

Original proposed Dec 2032
Current status Due Apr 2033

Revised projection

The completion date has moved from December 2032 to April 2033, 4 months later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

Survey no 18/3 (P) and 19/1 (P), Hinjewadi, Mulshi, Pune is the plot this project is built on, as filed
Revenue village Hinjavadi (CT) · shown on this site as Hinjewadi
TalukaMulshi
Bounded north by By Nalla
Bounded east by By Survey No.19/2 property of Villas Sakhare
Bounded south by 45 Mtrs wide Road
Bounded west by By Survey No.18/4 property of Singh.

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerShankeshwar Homes Pvt Ltd
Registered officeShop No 9,10,15 And 16, B- Wing, B- Wing, Ground Floor , Mahalaxmi Heights, Survey No 32/7, Near Pimpri City Mall, Pimpri, Pune 411018

Professionals named on the filing

Architect GM Architects CA/2005/35384
Engineer Raghuveer Jambhale
Chartered Accountant Ganesh SUNIL Mandlecha 620213
Chartered Accountant NPSR & Associates 170951
Chartered Accountant NPSR & Associates 030518

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

21 April 2026 is when an advocate last certified the title to this land
Title report legal title report 70326.pdf 21 April 2026
Conveyance deed Hinjawadi 18 3 7-12.pdf 24 April 2026 7 older versions on file
Promoter's declaration, Form B Affidavit Cum Declaration - Developer (2).pdf 21 April 2026
Annexure A declaration Annexure A As per order No 50.pdf 24 April 2026

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberPR1261012600728
Promoter Shankeshwar Homes Pvt Ltd
Project typeResidential / Group Housing · Building development
LocalityHinjewadi — Mulshi taluka, pincode 411057
Applied on24 April 2026
Registered on10 June 2026
Completion, as first filed31 December 2032
Due30 April 2033 4 months later
Units declared164
Units sold None sold yet, all 164 on the market
Complaints0 on record with MahaRERA
Certificate on file Corrected certificate, issued 02 September 2026
Application referenceACK23032607506
Current statusActive
Record last changed 04 August 2026 · 2 months ago

Nothing has sold yet. The promoter's quarterly progress report says none of the 164 flats are gone, and the unit-by-unit list they file separately says the same: all 164 still unsold. On a project this new that is normal rather than a warning, and it means every carpet area filed here is still available. Either way, this is only as current as the last change to the record, 04 August 2026.

Common questions

Is Shankeshwar Kingsland Phase 1 registered with MahaRERA?
Yes. It is registered as PR1261012600728, filed on 10 June 2026, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Shankeshwar Kingsland Phase 1 due to be handed over?
The promoter has told MahaRERA April 2033. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Shankeshwar Kingsland Phase 1 been delayed?
Yes. The first date filed was December 2032. It now stands at April 2033, 4 months later.
What does a flat in Shankeshwar Kingsland Phase 1 cost?
Nothing has been registered in this project yet, so it has no price of its own. Units the same size elsewhere in Hinjewadi have registered at ₹11,089–12,349 per square foot of carpet — the neighbourhood, not this building.
How many flats are left in Shankeshwar Kingsland Phase 1?
43 of 164 were still unsold at the promoter's last filing, in 2, 3 BHK, from 640–1,151 sq ft of carpet.
Are there complaints against Shankeshwar Kingsland Phase 1?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Shankeshwar Kingsland Phase 1?
Shankeshwar Homes Pvt Ltd, as the promoter named on the registration.

Check this yourself

This page restates one public record as we read it on 23 September 2026. The authority's own page for PR1261012600728 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.

MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.

Other projects in Hinjewadi