RERA registered P52100054765 Completed
Prime Space
Dudulgaon, Pune · Residential / Group Housing by Nath Estate
Official record Updated from the register 02 October 2026. Anything filed since then is not here yet.
In short
Prime Space in Dudulgaon is MahaRERA-registered (P52100054765) and was handed over in August 2026. Buyers have already registered 24 sales here at a median ₹6,681 per sq ft of carpet — not an asking price. Nath Estate is the promoter.
- Sold here at
- ₹6,681
- per sq ft, 24 registered sales
- Available
- 2, 3 BHK
- 14 left · 627–817 sq ft
- Now due
- Aug 2026
- 8 months later than first promised
Where this is
Dudulgaon, PCMC, Pune, 412105
The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.
Flat sizes on file
All 48 flats are filed unit by unit with the authority, the highest on floor 6. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.
2 BHK 24 units · 1 available
3 BHK 24 units · 13 available
18 / 48
38% absorption rate · the promoter's two filings disagree
Visual area guide See what the filed sizes feel like 2 generic footprints scaled from the registered carpet areas.
What each size looks like
Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.
2 BHK 24 flats · 1 available
627 sq ft carpet as drawn
- Carpet, filed
- 627 sq ft
- Built-up
- about 752 sq ft
- Super built-up
- about 878 sq ft
Every room in this flat
Living and dining about 183 sq ft, Master bedroom about 122 sq ft, Second bedroom about 97 sq ft, Kitchen about 73 sq ft, Bath about 43 sq ft, Balcony about 43 sq ft, Second bath about 37 sq ft, Passage about 30 sq ft.
3 BHK 24 flats · 13 available
817 sq ft carpet as drawn, from 761–817 sq ft filed in this configuration
- Carpet, filed
- 817 sq ft
- Built-up
- about 980 sq ft
- Super built-up
- about 1,144 sq ft
Every room in this flat
Living and dining about 201 sq ft, Master bedroom about 134 sq ft, Second bedroom about 107 sq ft, Third bedroom about 87 sq ft, Kitchen about 80 sq ft, Bath about 47 sq ft, Balcony about 47 sq ft, Second bath about 40 sq ft, Passage about 40 sq ft, Third bath about 33 sq ft.
The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.
What buyers actually paid
| Range across those sales | ₹5,425 to ₹7,756 per sq ft |
|---|---|
| Sold and booked | 24 sold, 0 booked |
| Still available | 14 flats, 627–817 sq ft |
A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold flats carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.
Timeline audit
Revised projection
The completion date has moved from December 2025 to August 2026, 8 months later, on the promoter's own revised filing.
Buyers who took possession late here may still have had a claim under section 18 of the Real Estate (Regulation and Development) Act, which entitles them to interest for every month of delay beyond the date in their agreement. More usefully for anyone buying today, this is a record of how this promoter performed against their own filed date.
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.
The land itself
| Revenue village | Dudulgaon |
|---|---|
| Taluka | Haveli |
| Street, as filed | Moshi - Alandi Road |
| Bounded north by | Gat No 193 |
| Bounded east by | Gat No 192 |
| Bounded south by | 18 mtr DP Road |
| Bounded west by | Gat No 194 |
Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.
"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.
Who is behind this project
Filed by the promoter with MahaRERA.
| Promoter on the register | Nath Estate |
|---|---|
| Registered office | Ground Floor, Landmarkk Luxuria, Gat No.120, Savtamali Nagar, Pune 412105 |
Professionals named on the filing
| Architect | Arcon Associates CA/2010/48607 |
|---|---|
| Engineer | Kiran Shivaji Patil |
| Engineer | Strudcom Consultants Pvt Ltd |
| Chartered Accountant | Ratikant Ranganath Pingale 103811 |
| Chartered Accountant | Snehal 174075 |
| Chartered Accountant | V S A P & Company 134211 |
The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.
Title and ownership papers
| Title report Legal Title Report 193.pdf | 10 November 2023 |
|---|---|
| Conveyance deed 193 Satbara.pdf | 13 January 2026 |
| Promoter's declaration, Form B Form B Affidavit cum Declaration.pdf | 10 November 2023 |
No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.
So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.
RERA filing records
View allEvery figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.
| Field | As filed with MahaRERA |
|---|---|
| Registration number | P52100054765 |
| Promoter | Nath Estate |
| Project type | Residential / Group Housing · Building development |
| Locality | Dudulgaon — Haveli taluka, pincode 412105 |
| Applied on | 11 November 2023 |
| Registered on | 12 February 2024 |
| Completion, as first filed | 31 December 2025 |
| Handed over | 31 August 2026 8 months later |
| Units declared | 48 |
| Units sold | 18 of 48 sold (38%), 30 still unsoldfilings disagree |
| Complaints | 0 on record with MahaRERA |
| Certificate on file | Extension certificate, issued 20 August 2026 |
| Application reference | REA52100149370 |
| Current status | Completed |
| Record last changed | 22 May 2026 · 4 months ago |
Where the sold count comes from, and whether it holds up. 18 of 48 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. And here the promoter's two filings do not agree. The quarterly report says 18 of 48 sold, leaving 30. The unit-by-unit list they file separately covers 48 flats and marks 24 sold with 14 left. We show both rather than quietly pick one, and the number to distrust is what is still available — ask the promoter which filing is current before believing a flat is free. Either way, this is only as current as the last change to the record, 22 May 2026.
Common questions
- Is Prime Space registered with MahaRERA?
- Yes. It is registered as P52100054765, filed on 12 February 2024, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
- Has Prime Space been handed over?
- Yes. The completion date on the register is August 2026.
- Has Prime Space been delayed?
- Yes. The first date filed was December 2025. It now stands at August 2026, 8 months later.
- What did buyers actually pay in Prime Space?
- A median of ₹6,681 per square foot of carpet, across 24 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
- How many flats are left in Prime Space?
- 14 of 48 were still unsold at the promoter's last filing, in 2, 3 BHK, from 627–817 sq ft of carpet.
- Are there complaints against Prime Space?
- None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
- Who is building Prime Space?
- Nath Estate, as the promoter named on the registration.
Check this yourself
This page restates one public record as we read it on 02 October 2026. The authority's own page for P52100054765 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.
MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.
Other projects in Dudulgaon
Stock image
- Registered here
- ₹5,661
- On offer
- 1, 3 BHK + shops
- Done
- Oct 2026
- Units
- 100
- Carpet
- 287–931
- Sold at
- ₹44.3 lakh
Stock image
- Nearby
- ₹6,275–6,850
- On offer
- 2, 3 BHK +2 more
- Due
- Feb 2032
- Units
- 126
- Carpet
- 213–793
- Typical unit
- ~₹41.7 lakh
Stock image
- Nearby
- ₹6,275–6,850
- On offer
- 2, 3 BHK
- Due
- Jun 2029
- Units
- 97
- Carpet
- 629–816
- Typical flat
- ~₹49.4 lakh