Fusion Towers Phase Iii

Bhoirwadi, Pune · Residential / Group Housing by Rama Synergy Spaces

Official record Updated from the register 28 October 2026. Anything filed since then is not here yet.

In short

Fusion Towers Phase Iii in Bhoirwadi is MahaRERA-registered (P52100049215) and still under construction, with possession filed for November 2026. Buyers have already registered 74 sales here at a median ₹8,948 per sq ft of carpet — not an asking price. 1 complaint sits on the filing. Rama Synergy Spaces is the promoter.

Stock image, not a photograph of Fusion Towers Phase Iii Stock image
Where
Bhoirwadi
pincode 411057
Sold here at
₹8,948
per sq ft, 74 registered sales
Available
2 BHK
5 left · 595–602 sq ft
Now due
Nov 2026
16 months later than first promised
A stock photograph, not Fusion Towers Phase Iii. We have no picture of this site yet.
Plot Demarcation

Land & Survey Location

Official parcel address and geographic coordinates as declared to MahaRERA.

Jurisdiction Bhoirwadi · Mulshi

Bhoirwadi, PMRDA, Pune, 411057

Street map of Bhoirwadi centred on the coordinate filed for Fusion Towers Phase Iii, about 1.4 km across.
Streets within about 700 m of the pin the promoter filed. Map data © OpenStreetMap contributors.
Village Bhoirwadi
Taluka Mulshi
Pincode 411057
Promoter Pin Coordinates 18.587581, 73.682939

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

Unit sizes on file

All 91 units are filed unit by unit with the authority, the highest on floor 10. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

Configuration Mix & Volume Proportional share of project density
91 Total Licenced Units
Dominant Typology • 86.8% of tower

2 BHK Residences

5 Available 79 registered total
Estimated Market Window ₹53.2 lakh – ₹53.9 lakh
Locality Benchmark ₹8,948 / sq ft
Carpet Variations as Filed Span: 594 to 602 sq ft
594 sq ft 55.23 sq m 5 units
595 sq ft 55.3 sq m 5 units
596 sq ft 55.33 sq m 15 units
597 sq ft 55.45 sq m 10 units
598 sq ft 55.6 sq m 5 units
599 sq ft 55.65 sq m 5 units
600 sq ft 55.73 sq m 4 units
601 sq ft 55.81 sq m 10 units
602 sq ft 55.89 sq m 20 units
Govt ASR Base: ₹22.7 lakh – ₹23 lakh 5 of 79 available
Commercial Footprint • 13.2% of project

Shops Suite

0 Available 12 registered total
Estimated Market Window
Carpet Variations as Filed Span: 277 to 711 sq ft
277 sq ft 25.76 sq m 1 unit
387 sq ft 35.95 sq m 1 unit
389 sq ft 36.13 sq m 1 unit
517 sq ft 48.0 sq m 1 unit
545 sq ft 50.63 sq m 1 unit
556 sq ft 51.69 sq m 1 unit
566 sq ft 52.58 sq m 1 unit
579 sq ft 53.83 sq m 1 unit
598 sq ft 55.59 sq m 2 units
701 sq ft 65.15 sq m 1 unit
711 sq ft 66.02 sq m 1 unit
None available

Carpet Area vs. Loading Factor Arithmetic

How statutory carpet translates to standard Pune market quoted areas (+20% Built-up, +40% Super Built-up)

Unit Configuration Statutory RERA Carpet (Actual) Approx Built-up (+20%) Super Built-up (+40% Loading) Available Inventory
2 BHK 594 – 602 sq ft (55.23 – 55.93 sq m) ~713 – 722 sq ft ~832 – 843 sq ft 5 left of 79
Shops 277 – 711 sq ft (25.76 – 66.02 sq m) ~332 – 853 sq ft ~388 – 995 sq ft 0 left of 12
Units sold

85 / 91

Nearly sold out

93% absorption rate · the promoter's two filings disagree

Visual area guide See what the filed sizes feel like 1 generic footprint scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a unit that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that unit, and each unit to its size against the largest one drawn below.

2 BHK 79 units · 5 available

602 sq ft carpet as drawn, from 594–602 sq ft filed in this configuration

Carpet, filed
602 sq ft
Built-up
about 722 sq ft
Super built-up
about 843 sq ft
Every room in this unit

Living and dining about 175 sq ft, Master bedroom about 117 sq ft, Second bedroom about 94 sq ft, Kitchen about 70 sq ft, Bath about 41 sq ft, Balcony about 41 sq ft, Second bath about 35 sq ft, Passage about 29 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹8,948 per sq ft of carpet, median of 74 registered sales
Range across those sales ₹6,859 to ₹10,588 per sq ft
Sold and booked 85 sold, 1 booked
Still available 5 units, 277–711 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold units carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

Filing Compliance

Timeline audit & delivery schedule

Possession milestones tracked directly against original MahaRERA declarations.

Filing State Revised (+16 months)
Original Baseline
Jul 2025
Declared at registration
Current Statutory Date
Due
Nov 2026
16 months later than filed

Revised delivery projection

The completion date has moved from July 2025 to November 2026, 16 months later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

S. No. 41/A/5, 41/A/14, 41/A/15, 41/A/16 is the plot this project is built on, as filed
Revenue village Bhoirwadi
TalukaMulshi
Street, as filed MIDC Main road
Bounded north by Open space 3 and parking building
Bounded east by Part of Fusion Towers future phase
Bounded south by 15 mtr wide internal road
Bounded west by 15 mtr wide internal road

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerRama Synergy Spaces
Registered office10th Floor, Rama Equator, Morwadi, Near Pcmc, Pimpri, Pune 411018

Professionals named on the filing

Architect VKa Architecture CA/84/8465
Engineer Ajit Kolekar
Engineer Akshay Nigade EN16-32269
Engineer Deepali Vilas Phulpagar
Chartered Accountant L. B. Laddha & Co 010550
Chartered Accountant Madhusudan Jhanwar 121450

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Complaints filed with MahaRERA

1 case against this project, 1 with an order on record. Complainants' names are published by the authority; we leave them out. Quote the case number to look one up.

Case numberFiledOutcome
CC12600347 Jan 2026 Order passed Jan 2026

A complaint is not proof of wrongdoing, and a project with none is not necessarily well run — most buyers never file. What the pattern shows is whether disputes here reached the regulator and whether they were decided.

Title and ownership papers

15 November 2022 is when an advocate last certified the title to this land
Title report legal title report.pdf 15 November 2022 2 older versions on file
Promoter's declaration, Form B Form B declaration_compressed.pdf 23 November 2022

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100049215
Promoter Rama Synergy Spaces
Project typeResidential / Group Housing · Building development
LocalityBhoirwadi — Mulshi taluka, pincode 411057
Applied on23 November 2022
Registered on03 February 2023
Completion, as first filed31 July 2025
Due30 November 2026 16 months later
Units declared91
Units sold 85 of 91 sold (93%), 6 still unsoldfilings disagree
Complaints1 on record with MahaRERA
Certificate on file Corrected certificate, issued 24 August 2026
Application referenceREA52100124868
Current statusActive
Record last changed 13 March 2026 · 8 months ago

Where the sold count comes from, and whether it holds up. 85 of 91 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. And here the promoter's two filings do not agree. The quarterly report says 85 of 91 sold, leaving 6. The unit-by-unit list they file separately covers 91 units and marks 85 sold with 5 left. We show both rather than quietly pick one, and the number to distrust is what is still available — ask the promoter which filing is current before believing a unit is free. Either way, this is only as current as the last change to the record, 13 March 2026.

Public Due Diligence

Common questions & statutory checks

Direct answers to questions buyers ask, verified strictly against the MahaRERA filing and registered deed records.

Verified Checks 7 Direct Answers
Is Fusion Towers Phase Iii registered with MahaRERA?
Yes. It is registered as P52100049215, filed on 03 February 2023, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Fusion Towers Phase Iii due to be handed over?
The promoter has told MahaRERA November 2026. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Fusion Towers Phase Iii been delayed?
Yes. The first date filed was July 2025. It now stands at November 2026, 16 months later.
What did buyers actually pay in Fusion Towers Phase Iii?
A median of ₹8,948 per square foot of carpet, across 74 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many units are left in Fusion Towers Phase Iii?
5 of 91 were still unsold at the promoter's last filing, in 2 BHK, from 595–602 sq ft of carpet.
Are there complaints against Fusion Towers Phase Iii?
1 case has been filed with MahaRERA against this project. A complaint is an allegation that has been lodged, not a finding against the promoter.
Who is building Fusion Towers Phase Iii?
Rama Synergy Spaces, as the promoter named on the registration.

Verify Government Filings Yourself

This dossier restates public records as filed on 28 October 2026. The authority's own registry page for P52100049215 carries sanctioned layout drawings, escrow accounts, quarterly progress filings, and title documents.

MahaRERA requires a CAPTCHA first. That is their verification gate, not a broken link.

Other projects in Bhoirwadi

Stock image, not a photograph of Livmo Phase Ii Stock image
Registered here
₹9,193
On offer
2 BHK
Under construction

Livmo Phase Ii

Priyanka Builders · Bhoirwadi

77 sold

5 complaints

Slipped 2 years
Due
Dec 2026
Units
196
Carpet
482–535
Sold at
₹44.7 lakh
P52100049773