Image Realty Private Limited
10 RERA-registered projects in Pune, across 1 locality.
Under construction — 10 projects
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| Vanaha Verdant Elm I & Ii | Lavale | Dec 2030 | Mar 2032 | Under construction | 0% | 0 |
| Vanaha Springs T1 Willow | Lavale | Mar 2026 | Mar 2027 | Under construction | 100% | 1 |
| Vanaha Springs T2 Cedar | Lavale | Dec 2025 | Dec 2026 | Under construction | 100% | 6 |
| Vanaha Springs T3 Aspen | Lavale | Dec 2025 | Dec 2026 | Under construction | 96% | 3 |
| Golfland I and II | Lavale | Dec 2028 | Dec 2028 | Under construction | 93% | 0 |
| Golfland III and IV | Lavale | Dec 2028 | Dec 2028 | Under construction | 88% | 0 |
| Golfland V and VI | Lavale | Dec 2029 | Dec 2029 | Under construction | 94% | 0 |
| Golfland VII and VIII | Lavale | Dec 2029 | Dec 2029 | Under construction | 93% | 0 |
| Vanaha Verdant Mahogany I & Ii | Lavale | Jun 2030 | Jun 2030 | Under construction | 34% | 0 |
| Vanaha Verdant Retail | Lavale | Dec 2030 | Dec 2030 | Under construction | 0% | 0 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Image Realty Private Limited's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.