Registration ended P52100053683 Lapsed

Madhumati Chsl

Shivajinagar, Pune · Residential / Group Housing by Kotibhaskar Infrastructures &Developers Pvt.Ltd.

Official record Updated from the register 14 October 2026. Anything filed since then is not here yet.

This registration has lapsed. MahaRERA ends a registration when the completion date passes with no extension filed, and that is what has happened here — the date was September 2026. Construction may well be continuing, and a lapse is not a finding against the builder. It does mean the register no longer stands behind the dates and unit counts below, and that the RERA protections you would be buying under are not currently in force. Everything on this page is the promoter's last filing, kept here because it is the record of what was promised.

In short

Madhumati Chsl in Shivajinagar was MahaRERA-registered as P52100053683, but that registration has lapsed. Buyers have already registered 9 sales here at a median ₹26,829 per sq ft of carpet — not an asking price. About 38% of the 24 units are sold. Kotibhaskar Infrastructures &Developers Pvt.Ltd. is the promoter.

Stock image, not a photograph of Madhumati Chsl Stock image
Where
Shivajinagar
pincode 411004
Sold here at
₹26,829
per sq ft, 9 registered sales
Available
2, 3, 4 BHK
15 left · 803–2,992 sq ft
Was due
Sep 2026
14 days past its date, not handed over
A stock photograph, not Madhumati Chsl. We have no picture of this site yet.
Plot Demarcation

Land & Survey Location

Official parcel address and geographic coordinates as declared to MahaRERA.

Jurisdiction Shivajinagar Bhamburda · Pune City

Shivajinagar, PMC, Pune, 411004

Village Shivajinagar Bhamburda
Taluka Pune City
Pincode 411004

No coordinate was filed for this project, so this searches Maps by name and locality rather than dropping a pin we cannot vouch for.

Flat sizes on file

All 24 flats are filed unit by unit with the authority, the highest on floor 13. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

Configuration Mix & Volume Proportional share of project density
24 Total Licenced Units
Residential Typology • 8.3% of tower

2 BHK Residences

2 Available 2 registered total
Estimated Market Window ₹2.2 crore – ₹2.4 crore
Locality Benchmark ₹26,829 / sq ft
Carpet Variations as Filed Span: 803 to 896 sq ft
803 sq ft 74.62 sq m 1 unit
896 sq ft 83.28 sq m 1 unit
2 of 2 available
Executive Typology • 8.3% of tower

3 BHK Residences

2 Available 2 registered total
Estimated Market Window ₹2.6 crore – ₹2.7 crore
Locality Benchmark ₹26,829 / sq ft
Carpet Variations as Filed Span: 984 to 988 sq ft
984 sq ft 91.4 sq m 1 unit
988 sq ft 91.82 sq m 1 unit
2 of 2 available
Dominant Typology • 79.2% of tower

4 BHK Residences

11 Available 19 registered total
Estimated Market Window ₹3.5 crore – ₹8 crore
Locality Benchmark ₹26,829 / sq ft
Carpet Variations as Filed Span: 1290 to 2992 sq ft
1290 sq ft 119.89 sq m 1 unit
1392 sq ft 129.35 sq m 1 unit
1426 sq ft 132.48 sq m 1 unit
1448 sq ft 134.51 sq m 1 unit
1450 sq ft 134.71 sq m 1 unit
1454 sq ft 135.08 sq m 1 unit
1493 sq ft 138.75 sq m 1 unit
1506 sq ft 139.93 sq m 1 unit
1509 sq ft 140.18 sq m 1 unit
1532 sq ft 142.29 sq m 1 unit
1549 sq ft 143.87 sq m 1 unit
1577 sq ft 146.47 sq m 2 units
1554 sq ft 144.4 sq m 1 unit
1656 sq ft 153.87 sq m 1 unit
1681 sq ft 156.2 sq m 1 unit
1687 sq ft 156.76 sq m 1 unit
1701 sq ft 158.0 sq m 1 unit
2992 sq ft 277.97 sq m 1 unit
Govt ASR Base: ₹2.9 crore 11 of 19 available
Residential Typology • 4.2% of tower

5 BHK Residences

0 Available 1 registered total
Estimated Market Window ₹8.1 crore
Locality Benchmark ₹26,829 / sq ft
Carpet Variations as Filed Span: 3027 sq ft
3027 sq ft 281.18 sq m 1 unit
None available

Carpet Area vs. Loading Factor Arithmetic

How statutory carpet translates to standard Pune market quoted areas (+20% Built-up, +40% Super Built-up)

Unit Configuration Statutory RERA Carpet (Actual) Approx Built-up (+20%) Super Built-up (+40% Loading) Available Inventory
2 BHK 803 – 896 sq ft (74.62 – 83.28 sq m) ~964 – 1075 sq ft ~1124 – 1254 sq ft 2 left of 2
3 BHK 984 – 988 sq ft (91.4 – 91.82 sq m) ~1181 – 1186 sq ft ~1378 – 1383 sq ft 2 left of 2
4 BHK 1290 – 2992 sq ft (119.89 – 277.97 sq m) ~1548 – 3590 sq ft ~1806 – 4189 sq ft 11 left of 19
5 BHK 3027 sq ft (281.18 sq m) ~3632 sq ft ~4238 sq ft 0 left of 1
Units sold

9 / 24

Early sales

38% absorption rate

Visual area guide See what the filed sizes feel like 4 generic footprints scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

2 BHK 2 flats · 2 available

803 sq ft carpet as drawn, from 803–896 sq ft filed in this configuration

Carpet, filed
803 sq ft
Built-up
about 964 sq ft
Super built-up
about 1,124 sq ft
Every room in this flat

Living and dining about 234 sq ft, Master bedroom about 156 sq ft, Second bedroom about 125 sq ft, Kitchen about 94 sq ft, Bath about 55 sq ft, Balcony about 55 sq ft, Second bath about 47 sq ft, Passage about 39 sq ft.

3 BHK 2 flats · 2 available

984 sq ft carpet as drawn, from 984–988 sq ft filed in this configuration

Carpet, filed
984 sq ft
Built-up
about 1,181 sq ft
Super built-up
about 1,378 sq ft
Every room in this flat

Living and dining about 242 sq ft, Master bedroom about 161 sq ft, Second bedroom about 129 sq ft, Third bedroom about 105 sq ft, Kitchen about 97 sq ft, Bath about 56 sq ft, Balcony about 56 sq ft, Second bath about 48 sq ft, Passage about 48 sq ft, Third bath about 40 sq ft.

4 BHK 19 flats · 11 available

1,577 sq ft carpet as drawn, from 1,290–2,992 sq ft filed in this configuration

Carpet, filed
1,577 sq ft
Built-up
about 1,892 sq ft
Super built-up
about 2,208 sq ft
Every room in this flat

Living and dining about 350 sq ft, Master bedroom about 234 sq ft, Second bedroom about 187 sq ft, Third bedroom about 152 sq ft, Kitchen about 140 sq ft, Fourth bedroom about 140 sq ft, Bath about 82 sq ft, Balcony about 82 sq ft, Passage about 82 sq ft, Second bath about 70 sq ft, Third bath about 58 sq ft.

5 BHK 1 flat · none available

3,027 sq ft carpet as drawn

Carpet, filed
3,027 sq ft
Built-up
about 3,632 sq ft
Super built-up
about 4,238 sq ft
Every room in this flat

Living and dining about 618 sq ft, Master bedroom about 412 sq ft, Second bedroom about 329 sq ft, Third bedroom about 268 sq ft, Kitchen about 247 sq ft, Fourth bedroom about 247 sq ft, Fifth bedroom about 227 sq ft, Passage about 165 sq ft, Bath about 144 sq ft, Balcony about 144 sq ft, Second bath about 124 sq ft, Third bath about 103 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹26,829 per sq ft of carpet, median of 9 registered sales
Range across those sales ₹18,637 to ₹30,146 per sq ft
Sold and booked 8 sold, 1 booked
Still available 15 flats, 803–3027 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold flats carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

Filing Compliance

Timeline audit & delivery schedule

Possession milestones tracked directly against original MahaRERA declarations.

Filing State Past Due 14 days past its date
Original Baseline
Mar 2026
Declared at registration
Current Statutory Date
Was due
Sep 2026
14 days past its date past due

Past handover deadline

The filing date of September 2026 has passed without completion being certified on the register (14 days past its date ago).

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

CTS NO 768 / 7+8, FINAL PLOT NO. 243/7+8 is the plot this project is built on, as filed
Revenue village Shivajinagar Bhamburda · shown on this site as Shivajinagar
TalukaPune City
Street, as filed PYC GYMKHANA
Bounded north by FINAL PLOT NO 243
Bounded east by FINAL PLOT NO 243
Bounded south by ROAD
Bounded west by ROAD

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerKotibhaskar Infrastructures &Developers Pvt.Ltd.
Registered officeF.P No. 71/A/1, Gurukrupa, Lane No. 15, Prabhat Road, Diagonally Opp. Symboisis School, Erandwane, Pune 411004

Professionals named on the filing

Architect Shinde Joshi and Associates CA/98/23512
Engineer Shridhar Shet na
Engineer Virendra Shrimant Daingade REG/PMC/STE/3053/23
Chartered Accountant Amit Anil Shende 132703
Chartered Accountant Omkar Chandak 163445

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

12 October 2023 is when an advocate last certified the title to this land
Title report 1 LG-Madhumati - legal Title Report -Format-A (merged)_compressed.pdf 12 October 2023
Promoter's declaration, Form B LG-Madhumati-Form B-20092023.pdf 27 September 2023

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100053683
Promoter Kotibhaskar Infrastructures &Developers Pvt.Ltd.
Project typeResidential / Group Housing · Building development
LocalityShivajinagar — Pune City taluka, pincode 411004
Applied on13 October 2023
Registered on22 November 2023
Completion, as first filed11 March 2026
Was due30 September 2026 7 months later
Units declared24
Units sold 9 of 24 sold (38%), 15 still unsold
Complaints0 on record with MahaRERA
Certificate on file Corrected certificate, issued 01 October 2026
Application referenceREA52100147926
Current statusLapsed
Record last changed 29 April 2026 · 6 months ago

Where the sold count comes from, and whether it holds up. 9 of 24 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 24 flats and reaches the same answer — 8 sold, every one with money recorded as received against a named flat, 1 booked with a price agreed but nothing received yet, and 15 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 29 April 2026.

Public Due Diligence

Common questions & statutory checks

Direct answers to questions buyers ask, verified strictly against the MahaRERA filing and registered deed records.

Verified Checks 6 Direct Answers
Is Madhumati Chsl registered with MahaRERA?
It was, as P52100053683, filed on 22 November 2023. That registration has since lapsed. A promoter may not advertise, market or sell in a project whose registration is not current, and a lapse does not by itself say the building has stopped.
When was Madhumati Chsl due to be handed over?
September 2026, and that date has passed without a handover being filed — 14 days ago. Section 18 of the Act gives an allottee a remedy when a promoter misses the date in the agreement.
What did buyers actually pay in Madhumati Chsl?
A median of ₹26,829 per square foot of carpet, across 9 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many flats are left in Madhumati Chsl?
15 of 24 were still unsold at the promoter's last filing, in 2, 3, 4 BHK, from 803–2,992 sq ft of carpet.
Are there complaints against Madhumati Chsl?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Madhumati Chsl?
Kotibhaskar Infrastructures &Developers Pvt.Ltd., as the promoter named on the registration.

Verify Government Filings Yourself

This dossier restates public records as filed on 14 October 2026. The authority's own registry page for P52100053683 carries sanctioned layout drawings, escrow accounts, quarterly progress filings, and title documents.

MahaRERA requires a CAPTCHA first. That is their verification gate, not a broken link.

Other projects in Shivajinagar

Stock image, not a photograph of Kamalini Stock image
Registered here
₹12,965
On offer
3 BHK
Under construction

Kamalini

Dreamforge Ventures LLP · Shivajinagar

27 sold
Slipped 4 months
Due
Apr 2030
Units
15
Carpet
935–1,410
Sold at
₹1.4 crore
PR1260002501245
Stock image, not a photograph of Krupa Stock image
Nearby
₹21,261–25,727
On offer
3, 4 BHK
Under construction

Krupa

Kamat Gandhi Venture · Shivajinagar

22 sold
Slipped 4 months
Due
Apr 2029
Units
9
Carpet
1,212–1,987
Typical flat
~₹2.8 crore
P52100078716