Z Zomefy

RERA registered P52100002395 Completed

Leisure Town Phase 1

Hadapsar, Pune · Residential / Group Housing by Sai Proviso Homes

Official record Updated from the register 10 October 2026. Anything filed since then is not here yet.

In short

Leisure Town Phase 1 in Hadapsar is MahaRERA-registered (P52100002395) and was handed over in December 2026. Buyers have already registered 521 sales here at a median ₹9,931 per sq ft of carpet — not an asking price. About 93% of the 560 units are sold. 59 complaints sit on the filing. Sai Proviso Homes is the promoter.

Stock image, not a photograph of Leisure Town Phase 1 Stock image
Where
Hadapsar
pincode 411028
Sold here at
₹9,931
per sq ft, 521 registered sales
Available
2 BHK
39 left · 516–563 sq ft
Now due
Dec 2026
4 years later than first promised
A stock photograph, not Leisure Town Phase 1. We have no picture of this site yet.

Where this is

Hadapsar, PMC, Pune, 411028

Village
Hadapsar
Taluka
Haveli
Pincode
411028
Coordinates
18.512951, 73.946242

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

Flat sizes on file

All 560 flats are filed unit by unit with the authority, the highest on floor 16. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

1 BHK 86 units · all sold

86 units 317 sq ft 29.41 sq m as filed

2 BHK 386 units · 39 available

32 units 516 sq ft 47.9 sq m as filed
24 units 523 sq ft 48.62 sq m as filed
38 units 525 sq ft 48.8 sq m as filed
10 units 526 sq ft 48.84–48.9 sq m as filed
54 units 528 sq ft 49.05–49.06 sq m as filed
10 units 530 sq ft 49.23 sq m as filed
14 units 532 sq ft 49.42–49.44 sq m as filed
19 units 538 sq ft 49.94 sq m as filed
40 units 540 sq ft 50.19 sq m as filed
24 units 542 sq ft 50.31 sq m as filed
48 units 546 sq ft 50.7 sq m as filed
19 units 552 sq ft 51.28 sq m as filed
24 units 554 sq ft 51.44 sq m as filed
6 units 562 sq ft 52.2 sq m as filed
12 units 563 sq ft 52.27–52.35 sq m as filed
12 units 566 sq ft 52.61 sq m as filed

3 BHK 88 units · all sold

24 units 712 sq ft 66.11 sq m as filed
20 units 714 sq ft 66.33 sq m as filed
24 units 766 sq ft 71.17 sq m as filed
20 units 769 sq ft 71.45 sq m as filed
Units sold

521 / 560

Nearly sold out

93% absorption rate

Visual area guide See what the filed sizes feel like 3 generic footprints scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

1 BHK 86 flats · none available

317 sq ft carpet as drawn

Carpet, filed
317 sq ft
Built-up
about 380 sq ft
Super built-up
about 444 sq ft
Every room in this flat

Living and dining about 119 sq ft, Master bedroom about 79 sq ft, Kitchen about 48 sq ft, Bath about 28 sq ft, Balcony about 28 sq ft, Passage about 16 sq ft.

2 BHK 386 flats · 39 available

528 sq ft carpet as drawn, from 516–566 sq ft filed in this configuration

Carpet, filed
528 sq ft
Built-up
about 634 sq ft
Super built-up
about 739 sq ft
Every room in this flat

Living and dining about 154 sq ft, Master bedroom about 103 sq ft, Second bedroom about 82 sq ft, Kitchen about 62 sq ft, Bath about 36 sq ft, Balcony about 36 sq ft, Second bath about 31 sq ft, Passage about 26 sq ft.

3 BHK 88 flats · none available

712 sq ft carpet as drawn, from 712–769 sq ft filed in this configuration

Carpet, filed
712 sq ft
Built-up
about 854 sq ft
Super built-up
about 997 sq ft
Every room in this flat

Living and dining about 175 sq ft, Master bedroom about 117 sq ft, Second bedroom about 93 sq ft, Third bedroom about 76 sq ft, Kitchen about 70 sq ft, Bath about 41 sq ft, Balcony about 41 sq ft, Second bath about 35 sq ft, Passage about 35 sq ft, Third bath about 29 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹9,931 per sq ft of carpet, median of 521 registered sales
Range across those sales ₹5,717 to ₹14,670 per sq ft
Sold and booked 519 sold, 2 booked
Still available 39 flats, 317–769 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold flats carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

Timeline audit

Original proposed Dec 2022
Current status Handed over Dec 2026

Revised projection

The completion date has moved from December 2022 to December 2026, 4 years later, on the promoter's own revised filing.

Buyers who took possession late here may still have had a claim under section 18 of the Real Estate (Regulation and Development) Act, which entitles them to interest for every month of delay beyond the date in their agreement. More usefully for anyone buying today, this is a record of how this promoter performed against their own filed date.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

202/A, 202/B/1/1 to 7, 202/B/2, 202/B/3, 202/B/4 is the plot this project is built on, as filed
Revenue village Hadapsar
TalukaHaveli
Street, as filed Sadesatra Nali Road
Bounded north by proposed RP road and Amanora Township
Bounded east by Sade Satra Nali Road
Bounded south by PMC Road
Bounded west by proposed RP road and Amanora Township

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerSai Proviso Homes
Registered office1201/1301, Bhumiraj Costarica, Sector 18, Plot No 1 & 2, Palm Beach Road, Sanpada, Thane 400705

Professionals named on the filing

Architect Deshpande Dixit and associates
Architect Jagdish P Deshpande C.A.2008/42068
Architect Vishal Deshpande 25532325
Engineer GA Bhilare consultants pvt ltd
Engineer Toufik Gavandi
Chartered Accountant E.A. Patil &Associates LLP 108231
Chartered Accountant Praveen M Khatri & Co. 165119

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Complaints filed with MahaRERA

59 cases against this project, 50 with an order on record, filed between Jun 2020 and Feb 2026. Complainants' names are published by the authority; we leave them out. Quote the case number to look one up.

Case numberFiledOutcome
CC12600650 Feb 2026 No order on record
CC12600305 Jan 2026 No order on record
CC12600306 Jan 2026 No order on record
CC12600307 Jan 2026 No order on record
CC12600308 Jan 2026 No order on record
CC12600309 Jan 2026 No order on record
CC12600310 Jan 2026 No order on record
CC12600311 Jan 2026 No order on record
CC12600312 Jan 2026 No order on record
CC12502949 Aug 2025 Order passed Aug 2025
Show the remaining 49 cases
CC12502926 Aug 2025 Order passed Aug 2025
CC12502927 Aug 2025 Order passed Aug 2025
CC12502818 Aug 2025 Order passed Aug 2025
CC12502819 Aug 2025 Order passed Aug 2025
CC12502808 Aug 2025 Order passed Aug 2025
CC12502799 Aug 2025 Order passed Aug 2025
CC12502739 Aug 2025 Order passed Aug 2025
CC12502530 Jul 2025 Order passed Jul 2025
CC12502517 Jul 2025 Order passed Jul 2025
CC12502519 Jul 2025 Order passed Jul 2025
CC12502488 Jul 2025 Order passed Jul 2025
CC12502454 Jul 2025 Order passed Jul 2025
CC12502368 Jul 2025 Order passed Jul 2025
CC12502351 Jul 2025 Order passed Jul 2025
CC12502326 Jul 2025 Order passed Jul 2025
CC12502312 Jul 2025 Order passed Jul 2025
CC12502324 Jul 2025 Order passed Jul 2025
CC12502304 Jul 2025 Order passed Jul 2025
CC12502262 Jul 2025 Order passed Jul 2025
CC12502265 Jul 2025 Order passed Jul 2025
CC12502211 Jul 2025 Order passed Jul 2025
CC12502158 Jun 2025 Order passed Jun 2025
CC12502166 Jun 2025 Order passed Jun 2025
CC12502069 Jun 2025 Order passed Jun 2025
CC12502071 Jun 2025 Order passed Jun 2025
CC12502037 Jun 2025 Order passed Jun 2025
CC12502039 Jun 2025 Order passed Jun 2025
CC12502033 Jun 2025 Order passed Jun 2025
CC12502036 Jun 2025 Order passed Jun 2025
CC12502015 Jun 2025 Order passed Jun 2025
CC12502018 Jun 2025 Order passed Jun 2025
CC12502012 Jun 2025 Order passed Jun 2025
CC12502014 Jun 2025 Order passed Jun 2025
CC005000000137157 May 2022 Order passed May 2022
CC005000000064352 Aug 2020 Order passed Aug 2020
CC005000000064455 Aug 2020 Order passed Aug 2020
CC005000000064348 Jul 2020 Order passed Jul 2020
CC005000000064336 Jul 2020 Order passed Jul 2020
CC005000000064328 Jul 2020 Order passed Jul 2020
CC005000000064340 Jul 2020 Order passed Jul 2020
CC005000000064343 Jul 2020 Order passed Jul 2020
CC005000000064354 Jul 2020 Order passed Jul 2020
CC005000000064360 Jul 2020 Order passed Jul 2020
CC005000000064368 Jul 2020 Order passed Jul 2020
CC005000000064363 Jul 2020 Order passed Jul 2020
CC005000000064364 Jul 2020 Order passed Jul 2020
CC005000000064250 Jun 2020 Order passed Jun 2020
CC005000000064254 Jun 2020 Order passed Jun 2020
CC005000000064252 Jun 2020 Order passed Jun 2020

A complaint is not proof of wrongdoing, and a project with none is not necessarily well run — most buyers never file. What the pattern shows is whether disputes here reached the regulator and whether they were decided.

Title and ownership papers

18 February 2026 is when an advocate last certified the title to this land
Title report Title Report.pdf 18 February 2026 1 older version on file
Promoter's declaration, Form B Form - B Promoter.pdf 16 February 2026 5 older versions on file

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100002395
Promoter Sai Proviso Homes
Project typeResidential / Group Housing · Building development
LocalityHadapsar — Haveli taluka, pincode 411028
Applied on26 July 2017
Registered on31 July 2017
Completion, as first filed30 December 2022
Handed over31 December 2026 4 years later
Units declared560
Units sold 521 of 560 sold (93%), 39 still unsold
Complaints59 on record with MahaRERA
Certificate on file Corrected certificate, issued 14 May 2026
Application referenceREA52100007415
Current statusCompleted
Record last changed 18 April 2026 · 6 months ago

Where the sold count comes from, and whether it holds up. 521 of 560 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 560 flats and reaches the same answer — 519 sold, every one with money recorded as received against a named flat, 2 booked with a price agreed but nothing received yet, and 39 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 18 April 2026.

Common questions

Is Leisure Town Phase 1 registered with MahaRERA?
Yes. It is registered as P52100002395, filed on 31 July 2017, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
Has Leisure Town Phase 1 been handed over?
Yes. The completion date on the register is December 2026.
Has Leisure Town Phase 1 been delayed?
Yes. The first date filed was December 2022. It now stands at December 2026, 4 years later.
What did buyers actually pay in Leisure Town Phase 1?
A median of ₹9,931 per square foot of carpet, across 521 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many flats are left in Leisure Town Phase 1?
39 of 560 were still unsold at the promoter's last filing, in 2 BHK, from 516–563 sq ft of carpet.
Are there complaints against Leisure Town Phase 1?
59 cases have been filed with MahaRERA against this project. A complaint is an allegation that has been lodged, not a finding against the promoter.
Who is building Leisure Town Phase 1?
Sai Proviso Homes, as the promoter named on the registration.

Check this yourself

This page restates one public record as we read it on 10 October 2026. The authority's own page for P52100002395 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.

MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.

Other projects in Hadapsar