Z Zomefy

RERA registered P52100079030 Active

Singh Chs

Gokhalenagar, Pune · Residential / Group Housing by Chaphalkar Karandikar Developers

Official record Updated from the register 13 October 2026. Anything filed since then is not here yet.

In short

Singh Chs in Gokhalenagar is MahaRERA-registered (P52100079030) and still under construction, with possession filed for April 2029. Buyers have already registered 6 sales here at a median ₹20,700 per sq ft of carpet — not an asking price. About 20% of the 30 units are sold. 2 complaints sit on the filing. Chaphalkar Karandikar Developers is the promoter.

Stock image, not a photograph of Singh Chs Stock image
Where
Gokhalenagar
pincode 411016
Sold here at
₹20,700
per sq ft, 6 registered sales
Available
4 BHK
10 left · 1,180–1,407 sq ft
Now due
Apr 2029
4 months later than first promised
A stock photograph, not Singh Chs. We have no picture of this site yet.
Plot Demarcation

Land & Survey Location

Official parcel address and geographic coordinates as declared to MahaRERA.

Jurisdiction Pune (M Corp.) · Pune City

Gokhalenagar, Pune, 411016

Village Pune (M Corp.)
Taluka Pune City
Pincode 411016

No coordinate was filed for this project, so this searches Maps by name and locality rather than dropping a pin we cannot vouch for.

Flat sizes on file

All 30 flats are filed unit by unit with the authority, the highest on floor 7. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

Configuration Mix & Volume Proportional share of project density
30 Total Licenced Units
Residential Typology • 3.3% of tower

1 BHK Residences

0 Available 1 registered total
Estimated Market Window ₹1.2 crore
Locality Benchmark ₹20,700 / sq ft
Carpet Variations as Filed Span: 560 sq ft
560 sq ft 52.02 sq m 1 unit
None available
Executive Typology • 3.3% of tower

3 BHK Residences

0 Available 1 registered total
Estimated Market Window ₹2.3 crore
Locality Benchmark ₹20,700 / sq ft
Carpet Variations as Filed Span: 1126 sq ft
1126 sq ft 104.6 sq m 1 unit
None available
Dominant Typology • 93.3% of tower

4 BHK Residences

10 Available 28 registered total
Estimated Market Window ₹1.8 crore – ₹2.9 crore
Locality Benchmark ₹20,700 / sq ft
Carpet Variations as Filed Span: 877 to 1407 sq ft
877 sq ft 81.49 sq m 2 units
1180 sq ft 109.63 sq m 2 units
1181 sq ft 109.75 sq m 7 units
1260 sq ft 117.09 sq m 1 unit
1290 sq ft 119.87 sq m 3 units
1291 sq ft 119.9 sq m 6 units
1326 sq ft 123.2 sq m 1 unit
1407 sq ft 130.74 sq m 6 units
Govt ASR Base: ₹1.4 crore – ₹1.8 crore 10 of 28 available

Carpet Area vs. Loading Factor Arithmetic

How statutory carpet translates to standard Pune market quoted areas (+20% Built-up, +40% Super Built-up)

Unit Configuration Statutory RERA Carpet (Actual) Approx Built-up (+20%) Super Built-up (+40% Loading) Available Inventory
1 BHK 560 sq ft (52.02 sq m) ~672 sq ft ~784 sq ft 0 left of 1
3 BHK 1126 sq ft (104.6 sq m) ~1351 sq ft ~1576 sq ft 0 left of 1
4 BHK 877 – 1407 sq ft (81.49 – 130.74 sq m) ~1052 – 1688 sq ft ~1228 – 1970 sq ft 10 left of 28
Units sold

6 / 30

Early sales

20% absorption rate

Visual area guide See what the filed sizes feel like 3 generic footprints scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

1 BHK 1 flat · none available

560 sq ft carpet as drawn

Carpet, filed
560 sq ft
Built-up
about 672 sq ft
Super built-up
about 784 sq ft
Every room in this flat

Living and dining about 210 sq ft, Master bedroom about 140 sq ft, Kitchen about 84 sq ft, Bath about 49 sq ft, Balcony about 49 sq ft, Passage about 28 sq ft.

3 BHK 1 flat · none available

1,126 sq ft carpet as drawn

Carpet, filed
1,126 sq ft
Built-up
about 1,351 sq ft
Super built-up
about 1,576 sq ft
Every room in this flat

Living and dining about 277 sq ft, Master bedroom about 185 sq ft, Second bedroom about 148 sq ft, Third bedroom about 120 sq ft, Kitchen about 111 sq ft, Bath about 65 sq ft, Balcony about 65 sq ft, Second bath about 55 sq ft, Passage about 55 sq ft, Third bath about 46 sq ft.

4 BHK 28 flats · 10 available

1,181 sq ft carpet as drawn, from 877–1,407 sq ft filed in this configuration

Carpet, filed
1,181 sq ft
Built-up
about 1,417 sq ft
Super built-up
about 1,653 sq ft
Every room in this flat

Living and dining about 262 sq ft, Master bedroom about 175 sq ft, Second bedroom about 140 sq ft, Third bedroom about 114 sq ft, Kitchen about 105 sq ft, Fourth bedroom about 105 sq ft, Bath about 61 sq ft, Balcony about 61 sq ft, Passage about 61 sq ft, Second bath about 52 sq ft, Third bath about 44 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹20,700 per sq ft of carpet, median of 6 registered sales
Range across those sales ₹17,395 to ₹29,899 per sq ft
Sold and booked 1 sold, 5 booked
Still available 10 flats, 560–1407 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold flats carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

Filing Compliance

Timeline audit & delivery schedule

Possession milestones tracked directly against original MahaRERA declarations.

Filing State Revised (+4 months)
Original Baseline
Dec 2028
Declared at registration
Current Statutory Date
Due
Apr 2029
4 months later than filed

Revised delivery projection

The completion date has moved from December 2028 to April 2029, 4 months later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

FINAL PLOT No 469B/2 CTS No 1088/B BHAMBURDA SHIVAJI NAGAR is the plot this project is built on, as filed
Revenue village Pune (M Corp.) · shown on this site as Gokhalenagar
TalukaPune City
Street, as filed HARE KRISHNA MANDIR PATH
Bounded north by JILKAR BAUG
Bounded east by PROPERTY OF SHRI JONDHALE
Bounded south by 20 FT ROAD
Bounded west by SUMIT APARTMENTS

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerChaphalkar Karandikar Developers
Registered office111, Mangala Multiplex, Shivaji, Near Pmc Building, Shivajinagar, Pune 411005

Professionals named on the filing

Chartered Accountant JPNR & Associates 193944
Chartered Accountant Khire Khandekar and Kirloskar 136606

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Complaints filed with MahaRERA

2 cases against this project, 2 with an order on record, filed between Feb 2026 and Feb 2026. Complainants' names are published by the authority; we leave them out. Quote the case number to look one up.

Case numberFiledOutcome
SM12600136 Feb 2026 Order passed Feb 2026
SM12600137 Feb 2026 Order passed Feb 2026

A complaint is not proof of wrongdoing, and a project with none is not necessarily well run — most buyers never file. What the pattern shows is whether disputes here reached the regulator and whether they were decided.

Title and ownership papers

8 January 2025 is when an advocate last certified the title to this land
Title report Search Title Report PRAKASH.pdf 8 January 2025
Promoter's declaration, Form B AFFIDAVIT CUM DECLARATION FORM B Developer.pdf 8 January 2025

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100079030
Promoter Chaphalkar Karandikar Developers
Project typeResidential / Group Housing · Building development
LocalityGokhalenagar — Pune City taluka, pincode 411016
Applied on08 January 2025
Registered on31 January 2025
Completion, as first filed31 December 2028
Due30 April 2029 4 months later
Units declared30
Units sold 6 of 30 sold (20%), 24 still unsold
Complaints2 on record with MahaRERA
Certificate on file Original registration certificate, issued 31 January 2025
Application referenceREA52100167382
Current statusActive
Record last changed 31 January 2025 · 20 months ago

Where the sold count comes from, and whether it holds up. 6 of 30 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 30 flats and reaches the same answer — 1 sold, every one with money recorded as received against a named flat, 5 booked with a price agreed but nothing received yet, and 10 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 31 January 2025.

Public Due Diligence

Common questions & statutory checks

Direct answers to questions buyers ask, verified strictly against the MahaRERA filing and registered deed records.

Verified Checks 7 Direct Answers
Is Singh Chs registered with MahaRERA?
Yes. It is registered as P52100079030, filed on 31 January 2025, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Singh Chs due to be handed over?
The promoter has told MahaRERA April 2029. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Singh Chs been delayed?
Yes. The first date filed was December 2028. It now stands at April 2029, 4 months later.
What did buyers actually pay in Singh Chs?
A median of ₹20,700 per square foot of carpet, across 6 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many flats are left in Singh Chs?
10 of 30 were still unsold at the promoter's last filing, in 4 BHK, from 1,180–1,407 sq ft of carpet.
Are there complaints against Singh Chs?
2 cases have been filed with MahaRERA against this project. A complaint is an allegation that has been lodged, not a finding against the promoter.
Who is building Singh Chs?
Chaphalkar Karandikar Developers, as the promoter named on the registration.

Verify Government Filings Yourself

This dossier restates public records as filed on 13 October 2026. The authority's own registry page for P52100079030 carries sanctioned layout drawings, escrow accounts, quarterly progress filings, and title documents.

MahaRERA requires a CAPTCHA first. That is their verification gate, not a broken link.

Other projects in Gokhalenagar

Stock image, not a photograph of Indraprastha Stock image
Registered here
₹16,520
On offer
2, 3 BHK + 1 RK
Under construction

Indraprastha

Pranesh Homes LLP · Gokhalenagar

29 sold
Slipped 16 months
Due
Jul 2027
Units
31
Carpet
282–1,025
Sold at
₹1.5 crore
P52100049861