RERA registered PM1260002501313 Active
Radhe Shlok
Charholi, Pune · Mixed by Shruti Realty
Official record Updated from the register 21 September 2026. Anything filed since then is not here yet.
In short
Radhe Shlok in Charholi is MahaRERA-registered (PM1260002501313) and still under construction, with possession filed for December 2027. Buyers have already registered 12 sales here at a median ₹6,937 per sq ft of carpet — not an asking price. Shruti Realty is the promoter.
- Sold here at
- ₹6,937
- per sq ft, 12 registered sales
- Available
- 2 BHK, 3 BHK, Shops
- 13 left · 241–822 sq ft
- Now due
- Dec 2027
- 4 months later than first promised
Where this is
Charholi, PCMC, Pune, 412105
The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.
Unit sizes on file
All 39 units are filed unit by unit with the authority, the highest on floor 7. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.
2 BHK 16 units · 3 available
3 BHK 19 units · 9 available
Shops 4 units · 1 available
5 / 39
13% absorption rate · the promoter's two filings disagree
Visual area guide See what the filed sizes feel like 2 generic footprints scaled from the registered carpet areas.
What each size looks like
Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a unit that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that unit, and each unit to its size against the largest one drawn below.
2 BHK 16 units · 3 available
579 sq ft carpet as drawn, from 559–609 sq ft filed in this configuration
- Carpet, filed
- 579 sq ft
- Built-up
- about 695 sq ft
- Super built-up
- about 811 sq ft
Every room in this unit
Living and dining about 169 sq ft, Master bedroom about 112 sq ft, Second bedroom about 90 sq ft, Kitchen about 67 sq ft, Bath about 39 sq ft, Balcony about 39 sq ft, Second bath about 34 sq ft, Passage about 28 sq ft.
3 BHK 19 units · 9 available
822 sq ft carpet as drawn, from 778–822 sq ft filed in this configuration
- Carpet, filed
- 822 sq ft
- Built-up
- about 986 sq ft
- Super built-up
- about 1,151 sq ft
Every room in this unit
Living and dining about 202 sq ft, Master bedroom about 135 sq ft, Second bedroom about 108 sq ft, Third bedroom about 88 sq ft, Kitchen about 81 sq ft, Bath about 47 sq ft, Balcony about 47 sq ft, Second bath about 40 sq ft, Passage about 40 sq ft, Third bath about 34 sq ft.
The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.
What buyers actually paid
| Range across those sales | ₹6,213 to ₹7,597 per sq ft |
|---|---|
| Sold and booked | 15 sold, 0 booked |
| Still available | 13 units, 232–822 sq ft |
A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold units carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.
Timeline audit
Revised projection
The completion date has moved from August 2027 to December 2027, 4 months later, on the promoter's own revised filing.
Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.
The land itself
| Revenue village | Charoli · shown on this site as Charholi |
|---|---|
| Taluka | Haveli |
| Street, as filed | Chovisawadi |
| Bounded north by | 18 Meters DP Road |
| Bounded east by | 25 Feet Road |
| Bounded south by | Nitin Ranganath Dev and Other's Property |
| Bounded west by | Tulshiram Lapkir's Property |
Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.
"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.
Who is behind this project
Filed by the promoter with MahaRERA.
| Promoter on the register | Shruti Realty |
|---|---|
| Registered office | Sr. No. 95/1/A, Radhe Windsun, Kalibhint Road, Chovishawadi, Charholi Budruk, Pune 412105 |
Professionals named on the filing
| Architect | Precision Architects & Planner CA/2007/39429 |
|---|---|
| Engineer | Arrow Structural Consultants PCMC/STE/0132/2022 |
| Engineer | Ranjit Bharat Jagdale |
| Chartered Accountant | Bankim Patel & Associates 144829 |
The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.
Title and ownership papers
| Title report Legal Title report.pdf | 16 September 2025 |
|---|---|
| Promoter's declaration, Form B Declaration Form B.pdf | 16 September 2025 |
| Annexure A declaration Annexure-A.pdf | 16 September 2025 |
No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.
So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.
RERA filing records
View allEvery figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.
| Field | As filed with MahaRERA |
|---|---|
| Registration number | PM1260002501313 |
| Promoter | Shruti Realty |
| Project type | Mixed · Building development |
| Locality | Charholi — Haveli taluka, pincode 412105 |
| Applied on | 23 September 2025 |
| Registered on | 20 October 2025 |
| Completion, as first filed | 31 August 2027 |
| Due | 31 December 2027 4 months later |
| Units declared | 39 |
| Units sold | 5 of 39 sold (13%), 34 still unsoldfilings disagree |
| Complaints | 0 on record with MahaRERA |
| Certificate on file | Corrected certificate, issued 09 June 2026 |
| Application reference | ACK16092503408 |
| Current status | Active |
| Record last changed | 09 April 2026 · 5 months ago |
Where the sold count comes from, and whether it holds up. 5 of 39 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. And here the promoter's two filings do not agree. The quarterly report says 5 of 39 sold, leaving 34. The unit-by-unit list they file separately covers 39 units and marks 15 sold with 13 left. We show both rather than quietly pick one, and the number to distrust is what is still available — ask the promoter which filing is current before believing a unit is free. Either way, this is only as current as the last change to the record, 09 April 2026.
Common questions
- Is Radhe Shlok registered with MahaRERA?
- Yes. It is registered as PM1260002501313, filed on 20 October 2025, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
- When is Radhe Shlok due to be handed over?
- The promoter has told MahaRERA December 2027. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
- Has Radhe Shlok been delayed?
- Yes. The first date filed was August 2027. It now stands at December 2027, 4 months later.
- What did buyers actually pay in Radhe Shlok?
- A median of ₹6,937 per square foot of carpet, across 12 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
- How many units are left in Radhe Shlok?
- 13 of 39 were still unsold at the promoter's last filing, in 2, 3 BHK + shops, from 241–822 sq ft of carpet.
- Are there complaints against Radhe Shlok?
- None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
- Who is building Radhe Shlok?
- Shruti Realty, as the promoter named on the registration.
Check this yourself
This page restates one public record as we read it on 21 September 2026. The authority's own page for PM1260002501313 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.
MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.
Other projects in Charholi
Stock image
- Nearby
- ₹6,196
- On offer
- 1 BHK +2 more
13 complaints
- Due
- Dec 2028
- Units
- 599
- Carpet
- 195–303
- Typical unit
- ~₹12.1 lakh
Stock image
- Nearby
- ₹6,196–6,879
- On offer
- 1, 2 BHK +2 more
2 complaints
- Due
- Dec 2028
- Units
- 767
- Carpet
- 195–457
- Typical unit
- ~₹19.8 lakh
Stock image
- Nearby
- ₹6,196–6,879
- On offer
- 1, 2 BHK + shops
5 complaints
- Due
- Dec 2028
- Units
- 902
- Carpet
- 217–457
- Typical unit
- ~₹19.8 lakh