Fortune Developers

6 RERA-registered projects in Pune, across 4 localities.

4under construction
2delivered
0past their date
1complaints

Under construction — 4 projects

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
State Bank Of India Employees Himgauri Co Operative Housing Society Ltd Deccan Gymkhana Sep 2026 Jan 2027 Under construction 55% 0
Prashanti Co Operative Housing Society Limited Deccan Gymkhana Mar 2027 Jul 2027 Under construction 37% 0
Yashodhan Co-Operative Housing Society Deccan Gymkhana Mar 2028 Jul 2028 Under construction 14% 1
Vishwambhar Co-Operative Housing Society Limited Kothrud Dec 2026 Dec 2026 Under construction 65% 0
Advertisement
Track record Delivered — 2 projects Handed over; late deliveries are the best guide to the next deadline.

Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch.

ProjectLocalityPromised Handed over Late by SoldComplaints
Garud House Apartment Condominium Gokhalenagar Dec 2026 Dec 2026 On time 33% 0
Madhvachhaya Shivajinagar Jun 2025 Jun 2025 On time 36% 0

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Fortune Developers's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.