City Corporation Limited

7 RERA-registered projects in Pune, across 1 locality.

4under construction
3delivered
0past their date
3complaints

Under construction — 4 projects

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Amanora Arbano Towers 73,74,75 and 76 Hadapsar May 2028 May 2028 Under construction 98% 1
Amanora Arbano Towers 71 and 72 Hadapsar May 2028 May 2028 Under construction 98% 0
Amanora Gateway Towers 2 - Towers 102 and 103 Hadapsar Jun 2029 Jun 2029 Under construction 61% 1
Amanora Gateway Towers 2 – Tower 101 Hadapsar Dec 2030 Dec 2030 Under construction 34% 1
Advertisement
Track record Delivered — 3 projects Handed over; late deliveries are the best guide to the next deadline.

Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch. 1 of 3 arrived later than first promised, which is the closest thing on record to how this promoter treats a deadline.

ProjectLocalityPromised Handed over Late by SoldComplaints
Amanora Ascent Avenue Hadapsar Jun 2025 Sep 2025 2 months 69% 0
Amanora Sweet Water Villa Plots Hadapsar Sep 2018 Sep 2018 On time 82% 0
Amanora Elevate Tower 47 Hadapsar Dec 2025 Dec 2025 On time 100% 0

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from City Corporation Limited's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.