Z Zomefy

RERA registered P52100018265 Completed

Rosewood Park

Wagholi, Pune · Residential / Group Housing by Shri Manibhadra Estates

Official record Updated from the register 04 October 2026. Anything filed since then is not here yet.

In short

Rosewood Park in Wagholi is MahaRERA-registered (P52100018265) and was handed over in December 2026. Buyers have already registered 23 sales here at a median ₹6,144 per sq ft of carpet — not an asking price. 1 complaint sits on the filing. Shri Manibhadra Estates is the promoter.

Stock image, not a photograph of Rosewood Park Stock image
Where
Wagholi
pincode 412207
Sold here at
₹6,144
per sq ft, 23 registered sales
Available
2 BHK
5 left · 584–835 sq ft
Now due
Dec 2026
2 years later than first promised
A stock photograph, not Rosewood Park. We have no picture of this site yet.

Where this is

Wagholi, PMC, Pune, 412207

Village
WAGHOLI
Taluka
Haveli
Pincode
412207
Coordinates
18.578866, 73.987420

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

Flat sizes on file

All 54 flats are filed unit by unit with the authority, the highest on floor 9. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

2 BHK 54 units · 5 available

2 units 572 sq ft 53.15 sq m as filed
2 units 575 sq ft 53.39 sq m as filed
2 units 576 sq ft 53.49 sq m as filed
2 units 584 sq ft 54.3 sq m as filed
3 units 687 sq ft 63.81 sq m as filed
4 units 715 sq ft 66.46 sq m as filed
5 units 723 sq ft 67.14 sq m as filed
4 units 731 sq ft 67.89 sq m as filed
5 units 737 sq ft 68.44–68.45 sq m as filed
4 units 742 sq ft 68.93 sq m as filed
7 units 793 sq ft 73.67 sq m as filed
5 units 835 sq ft 77.57 sq m as filed
6 further sizes, 9 units between them
1 unit 642 sq ft 59.65 sq m as filed
2 units 680 sq ft 63.22 sq m as filed
2 units 691 sq ft 64.19 sq m as filed
2 units 697 sq ft 64.78 sq m as filed
1 unit 739 sq ft 68.67 sq m as filed
1 unit 740 sq ft 68.75 sq m as filed
Units sold

26 / 54

Selling steadily

48% absorption rate · the promoter's two filings disagree

Visual area guide See what the filed sizes feel like 1 generic footprint scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

2 BHK 54 flats · 5 available

793 sq ft carpet as drawn, from 572–835 sq ft filed in this configuration

Carpet, filed
793 sq ft
Built-up
about 952 sq ft
Super built-up
about 1,110 sq ft
Every room in this flat

Living and dining about 231 sq ft, Master bedroom about 154 sq ft, Second bedroom about 123 sq ft, Kitchen about 92 sq ft, Bath about 54 sq ft, Balcony about 54 sq ft, Second bath about 46 sq ft, Passage about 38 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹6,144 per sq ft of carpet, median of 23 registered sales
Range across those sales ₹4,327 to ₹7,864 per sq ft
Sold and booked 23 sold, 0 booked
Still available 5 flats, 572–835 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold flats carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

Timeline audit

Original proposed Dec 2024
Current status Handed over Dec 2026

Revised projection

The completion date has moved from December 2024 to December 2026, 2 years later, on the promoter's own revised filing.

Buyers who took possession late here may still have had a claim under section 18 of the Real Estate (Regulation and Development) Act, which entitles them to interest for every month of delay beyond the date in their agreement. More usefully for anyone buying today, this is a record of how this promoter performed against their own filed date.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

GAT NO. 1106-1107 is the plot this project is built on, as filed
Revenue village WAGHOLI · shown on this site as Wagholi
TalukaHaveli
Street, as filed AVALHWADI ROAD, WAGHOLI
Bounded north by GAT NO 1109 PART
Bounded east by GAT NO 1108 PART
Bounded south by GAT NO 1107 PART
Bounded west by GAT NO 1106 PART

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerShri Manibhadra Estates
Registered officeOffice No 502, 502, Aurora Towers, West Wing, Hotel Aurora Towers, Mg Road, Camp, Pune 411001

Professionals named on the filing

Architect Vivek Garode CA/99/24888
Engineer Dinesh Bhandari
Engineer Girish Kumbhar 0174577
Engineer Parag Chopada
Engineer Vishal Rananaware
Chartered Accountant Chaudhari Agarwal & Associates 144540
Chartered Accountant Pratik Navlakha And Associates 152983
Chartered Accountant Vijay D Kendhe 035178

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Complaints filed with MahaRERA

1 case against this project, 1 with an order on record. Complainants' names are published by the authority; we leave them out. Quote the case number to look one up.

Case numberFiledOutcome
CC005000000064487 Aug 2020 Order passed Aug 2020

A complaint is not proof of wrongdoing, and a project with none is not necessarily well run — most buyers never file. What the pattern shows is whether disputes here reached the regulator and whether they were decided.

Title and ownership papers

6 September 2023 is when an advocate last certified the title to this land
Title report title and serch report-compressed.pdf 6 September 2023 6 older versions on file
Promoter's declaration, Form B Form B ROSEWOOD PARK-1-3.pdf 18 February 2025 2 older versions on file

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100018265
Promoter Shri Manibhadra Estates
Project typeResidential / Group Housing · Building development
LocalityWagholi — Haveli taluka, pincode 412207
Applied on11 October 2018
Registered on22 October 2018
Completion, as first filed30 December 2024
Handed over31 December 2026 2 years later
Units declared54
Units sold 26 of 54 sold (48%), 28 still unsoldfilings disagree
Complaints1 on record with MahaRERA
Certificate on file Extension certificate, issued 15 April 2026
Application referenceREA52100045268
Current statusCompleted
Record last changed 15 June 2026 · 4 months ago

Where the sold count comes from, and whether it holds up. 26 of 54 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. And here the promoter's two filings do not agree. The quarterly report says 26 of 54 sold, leaving 28. The unit-by-unit list they file separately covers 54 flats and marks 23 sold with 5 left. We show both rather than quietly pick one, and the number to distrust is what is still available — ask the promoter which filing is current before believing a flat is free. Either way, this is only as current as the last change to the record, 15 June 2026.

Common questions

Is Rosewood Park registered with MahaRERA?
Yes. It is registered as P52100018265, filed on 22 October 2018, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
Has Rosewood Park been handed over?
Yes. The completion date on the register is December 2026.
Has Rosewood Park been delayed?
Yes. The first date filed was December 2024. It now stands at December 2026, 2 years later.
What did buyers actually pay in Rosewood Park?
A median of ₹6,144 per square foot of carpet, across 23 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many flats are left in Rosewood Park?
5 of 54 were still unsold at the promoter's last filing, in 2 BHK, from 584–835 sq ft of carpet.
Are there complaints against Rosewood Park?
1 case has been filed with MahaRERA against this project. A complaint is an allegation that has been lodged, not a finding against the promoter.
Who is building Rosewood Park?
Shri Manibhadra Estates, as the promoter named on the registration.

Check this yourself

This page restates one public record as we read it on 04 October 2026. The authority's own page for P52100018265 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.

MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.

Other projects in Wagholi

Stock image, not a photograph of Lake Tower Stock image
Registered here
₹7,448
On offer
3 BHK
Ready to move

Lake Tower

Tushar Pramod Nagarkar · Wagholi

61 sold
Slipped 4.8 years
Done
Apr 2026
Units
87
Carpet
887
Sold at
₹44.9 lakh
P52100002281