RERA registered P52100078243 Active

Green Aura-1

Sangvi, Pune · Plotted by Bhagyashree Yuvraj Kakade

Official record Updated from the register 21 September 2026. Anything filed since then is not here yet.

In short

Green Aura-1 in Sangvi is MahaRERA-registered (P52100078243) and still under construction, with possession filed for July 2027. No registered sale rate is on file for this project or its locality yet. About 63% of the 19 units are sold. Bhagyashree Yuvraj Kakade is the promoter.

Stock image, not a photograph of Green Aura-1 Stock image
Where
Sangvi
pincode 410401
Price
Not filed
no agreement or valuation on the register
Available
Not filed
the promoter filed no unit list
Now due
Jul 2027
1.6 years later than first promised
A stock photograph, not Green Aura-1. We have no picture of this site yet.

Where this is

Sangvi, PCMC, Pune, 410401

Street map of Sangvi centred on the coordinate filed for Green Aura-1, about 1.4 km across.
Streets within about 700 m of the pin the promoter filed. Map data © OpenStreetMap contributors.
Village
Sangavi
Taluka
Mawal
Pincode
410401
Coordinates
18.524609, 73.878624

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

How much of this has sold

Carpet areas and the unit-by-unit breakdown are filed for most projects but are missing for this one, so the count below is all the register holds on what is being built here.

Units sold

12 / 19

Selling steadily

63% absorption rate

Timeline audit

Original proposed Dec 2025
Current status Due Jul 2027

Revised projection

The completion date has moved from December 2025 to July 2027, 1.6 years later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

68 (Part) is the plot this project is built on, as filed
Revenue village Sangavi · shown on this site as Sangvi
TalukaMawal
Street, as filed Mauje Sangavi
Bounded north by By Land out of G no 68 Owd by Kanta Maruti Pansare
Bounded east by By Land ad 0 H 34 A out of G No 68 Owd by Dimple
Bounded south by By Gat No 69
Bounded west by By land ad 0H 15A out of G No 68 Ond Rajdheera pvt

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerBhagyashree Yuvraj Kakade
Registered officeShop No 11, 11, Shubham Complex, Chakan Road, Talegaon Dabhade, Talegaon Chakan Road, Pune 410507

Professionals named on the filing

Architect Ajit Thakur ca/95/20454
Architect kaustubh Babar CA/2011/50998
Engineer Akash Temgire STATE/R/2025/APL/19711
Engineer Ankit Gupta .
Chartered Accountant Anita Limaye 032717
Chartered Accountant CA Priyesh Jain 194983
Chartered Accountant nilesh Raut 137790

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

18 November 2024 is when an advocate last certified the title to this land
Title report Legal Title Report 06092024 (Revised) New.pdf 18 November 2024
Promoter's declaration, Form B Form-B Affidavit 18092024.pdf 14 October 2024

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100078243
Promoter Bhagyashree Yuvraj Kakade
Project typePlotted · Plotted development
LocalitySangvi — Mawal taluka, pincode 410401
Applied on28 October 2024
Registered on29 November 2024
Completion, as first filed31 December 2025
Due31 July 2027 1.6 years later
Units declared19
Units sold 12 of 19 sold (63%), 7 still unsold
Complaints0 on record with MahaRERA
Certificate on file Extension certificate, issued 14 August 2026
Application referenceREA52100165404
Current statusActive
Record last changed 07 January 2026 · 8 months ago

Where the sold count comes from, and whether it holds up. 12 of 19 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. There is no unit-by-unit filing on record for this project to check it against, so this is a single unverified number. Either way, this is only as current as the last change to the record, 07 January 2026.

Common questions

Is Green Aura-1 registered with MahaRERA?
Yes. It is registered as P52100078243, filed on 29 November 2024, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Green Aura-1 due to be handed over?
The promoter has told MahaRERA July 2027. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Green Aura-1 been delayed?
Yes. The first date filed was December 2025. It now stands at July 2027, 1.6 years later.
Are there complaints against Green Aura-1?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Green Aura-1?
Bhagyashree Yuvraj Kakade, as the promoter named on the registration.

Check this yourself

This page restates one public record as we read it on 21 September 2026. The authority's own page for P52100078243 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.

MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.

Other projects in Sangvi

Stock image, not a photograph of Santiago Sunrise Stock image
Registered here
₹10,709
On offer
3 BHK + shops
Under construction

Santiago Sunrise

Santiago Realtech Ventures · Sangvi

81 sold
Slipped 4 months
Due
Apr 2028
Units
48
Carpet
286–795
Sold at
₹67.3 lakh
P52100077792
Stock image, not a photograph of Varad Classic Stock image
Registered here
₹8,290
On offer
2 BHK + shops
Under construction

Varad Classic

Vinay Sudam Kunjir, Ragini Rajesh Jagatap,Varsha Vijay Sonawane, And Srk Reality Through Sushma Rajendra Tanpure. Ketan Anil Murkute · Sangvi

18 sold
Due
Mar 2027
Units
56
Carpet
252–852
Sold at
₹61.9 lakh
P52100034474
Stock image, not a photograph of West 9 Buissness Arc Stock image
Valued from
₹6,277
On offer
Offices + shops
Under construction

West 9 Buissness Arc

S R K Realty & AS Developers · Sangvi

19 sold

1 complaint

Slipped 2.3 years
Due
Apr 2028
Units
74
Carpet
308–1,461
Sold at
₹32.8 lakh
P52100050051