RERA registered P52100055954 Active

The Arista

Pimple Nilakh, Pune · Residential / Group Housing by Cristallo Infra LLP

Official record Updated from the register 23 October 2026. Anything filed since then is not here yet.

In short

The Arista in Pimple Nilakh is MahaRERA-registered (P52100055954) and still under construction, with possession filed for December 2027. Buyers have already registered 8 sales here at a median ₹13,181 per sq ft of carpet — not an asking price. About 29% of the 31 units are sold. Cristallo Infra LLP is the promoter.

Stock image, not a photograph of The Arista Stock image
Where
Pimple Nilakh
pincode 411027
Sold here at
₹13,181
per sq ft, 8 registered sales
Available
3 BHK
16 left · 218–1,490 sq ft
Now due
Dec 2027
4 months later than first promised
A stock photograph, not The Arista. We have no picture of this site yet.
Plot Demarcation

Land & Survey Location

Official parcel address and geographic coordinates as declared to MahaRERA.

Jurisdiction Pimple Nilakh · Haveli

Pimple Nilakh, PCMC, Pune, 411027

Village Pimple Nilakh
Taluka Haveli
Pincode 411027
Promoter Pin Coordinates 18.586312, 73.784813

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

Flat sizes on file

All 31 flats are filed unit by unit with the authority, the highest on floor 8. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

Configuration Mix & Volume Proportional share of project density
31 Total Licenced Units
Dominant Typology • 93.5% of tower

3 BHK Residences

15 Available 29 registered total
Estimated Market Window ₹1.4 crore – ₹2 crore
Locality Benchmark ₹13,181 / sq ft
Carpet Variations as Filed Span: 1082 to 1490 sq ft
1082 sq ft 100.49 sq m 13 units
1084 sq ft 100.72 sq m 2 units
1188 sq ft 110.39 sq m 2 units
1480 sq ft 137.53 sq m 10 units
1490 sq ft 138.4 sq m 2 units
Govt ASR Base: ₹58.2 lakh – ₹80.1 lakh 15 of 29 available
Residential Typology • 6.5% of tower

Other Residences

1 Available 2 registered total
Estimated Market Window ₹28.7 lakh
Locality Benchmark ₹13,181 / sq ft
Carpet Variations as Filed Span: 218 sq ft
218 sq ft 20.25 sq m 2 units
Govt ASR Base: ₹11.7 lakh 1 of 2 available

Carpet Area vs. Loading Factor Arithmetic

How statutory carpet translates to standard Pune market quoted areas (+20% Built-up, +40% Super Built-up)

Unit Configuration Statutory RERA Carpet (Actual) Approx Built-up (+20%) Super Built-up (+40% Loading) Available Inventory
3 BHK 1082 – 1490 sq ft (100.49 – 138.4 sq m) ~1298 – 1788 sq ft ~1515 – 2086 sq ft 15 left of 29
Other 218 sq ft (20.25 sq m) ~262 sq ft ~305 sq ft 1 left of 2
Units sold

9 / 31

Early sales

29% absorption rate

Visual area guide See what the filed sizes feel like 1 generic footprint scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

3 BHK 29 flats · 15 available

1,082 sq ft carpet as drawn, from 1,082–1,490 sq ft filed in this configuration

Carpet, filed
1,082 sq ft
Built-up
about 1,298 sq ft
Super built-up
about 1,515 sq ft
Every room in this flat

Living and dining about 266 sq ft, Master bedroom about 177 sq ft, Second bedroom about 142 sq ft, Third bedroom about 115 sq ft, Kitchen about 106 sq ft, Bath about 62 sq ft, Balcony about 62 sq ft, Second bath about 53 sq ft, Passage about 53 sq ft, Third bath about 44 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What buyers actually paid

₹13,181 per sq ft of carpet, median of 8 registered sales
Range across those sales ₹7,396 to ₹13,961 per sq ft
Sold and booked 9 sold, 0 booked
Still available 16 flats, 218–1490 sq ft

A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold flats carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.

1 further sale is set aside. It divides out beyond ₹33,773 per sq ft, more than two and a half times this project's own median. A flat does not cost that much more than its neighbours on the same price list, so the usual cause is a carpet area filed too small for the agreement value printed beside it. Both figures are on the register exactly as shown — you can check them in the register itself — but no rate is computed from them here. Counted rather than quietly dropped.

Filing Compliance

Timeline audit & delivery schedule

Possession milestones tracked directly against original MahaRERA declarations.

Filing State Revised (+4 months)
Original Baseline
Aug 2027
Declared at registration
Current Statutory Date
Due
Dec 2027
4 months later than filed

Revised delivery projection

The completion date has moved from August 2027 to December 2027, 4 months later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

Survey No 24/1A/1/1,24/1B/1/1,24/1C/1/1,24/1D/1/1, CTS No 1214 is the plot this project is built on, as filed
Revenue village Pimple Nilakh
TalukaHaveli
Street, as filed Survey No 24/1A/1/1,24/1B/1/1 , 24/1C/1/1,24/1D/1/1, CTS No 1214
Bounded north by By road and property of Mr Taskar
Bounded east by By 12 Meter wide road and Military Land
Bounded south by By property belong to Mr D R Bavdhane and Sandhy
Bounded west by By Property held by Mr Meenakshi S Chaher

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerCristallo Infra LLP
Registered officeOffice No 4 S No 28/4/1/1, S No 28/4/1/1, Omkar Heights, Aundh Wakad Road, Jagtap Dairy, Pimple Nilakh, Pune 411027

Professionals named on the filing

Architect Cubix Architects Associates CA/2001/28514
Architect Patil and Bugade Associates
Engineer Bricklane
Engineer Rohinee Engineers
Chartered Accountant CA Pravin Pise and Associates
Chartered Accountant D. P. Padia & Co. 145412

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

12 April 2024 is when an advocate last certified the title to this land
Title report Advocate - Format A_11zon.pdf 12 April 2024
Promoter's declaration, Form B Form B Promoter.pdf 12 April 2024

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100055954
Promoter Cristallo Infra LLP
Project typeResidential / Group Housing · Building development
LocalityPimple Nilakh — Haveli taluka, pincode 411027
Applied on13 April 2024
Registered on02 May 2024
Completion, as first filed31 August 2027
Due31 December 2027 4 months later
Units declared31
Units sold 9 of 31 sold (29%), 22 still unsold
Complaints0 on record with MahaRERA
Certificate on file Original registration certificate, issued 02 May 2024
Application referenceREA52100157237
Current statusActive
Record last changed 24 March 2025 · 19 months ago

Where the sold count comes from, and whether it holds up. 9 of 31 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 31 flats and reaches the same answer — 9 sold, every one with money recorded as received against a named flat, and 16 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 24 March 2025.

Public Due Diligence

Common questions & statutory checks

Direct answers to questions buyers ask, verified strictly against the MahaRERA filing and registered deed records.

Verified Checks 7 Direct Answers
Is The Arista registered with MahaRERA?
Yes. It is registered as P52100055954, filed on 02 May 2024, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is The Arista due to be handed over?
The promoter has told MahaRERA December 2027. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has The Arista been delayed?
Yes. The first date filed was August 2027. It now stands at December 2027, 4 months later.
What did buyers actually pay in The Arista?
A median of ₹13,181 per square foot of carpet, across 8 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
How many flats are left in The Arista?
16 of 31 were still unsold at the promoter's last filing, in 3 BHK, from 218–1,490 sq ft of carpet.
Are there complaints against The Arista?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building The Arista?
Cristallo Infra LLP, as the promoter named on the registration.

Verify Government Filings Yourself

This dossier restates public records as filed on 23 October 2026. The authority's own registry page for P52100055954 carries sanctioned layout drawings, escrow accounts, quarterly progress filings, and title documents.

MahaRERA requires a CAPTCHA first. That is their verification gate, not a broken link.