Park Imperial Tower A

Hadapsar, Pune · Residential / Group Housing by Iqoniq shelters llp

Official record Updated from the register 30 October 2026. Anything filed since then is not here yet.

In short

Park Imperial Tower A in Hadapsar is MahaRERA-registered (PR1261012600792) and still under construction, with possession filed for April 2035. No sales are registered in this project yet. Units the same size elsewhere in Hadapsar have registered at ₹12,220 per sq ft of carpet — the neighbourhood, not this building. None of the units are filed as sold yet. Iqoniq shelters llp is the promoter.

Stock image, not a photograph of Park Imperial Tower A Stock image
Where
Hadapsar
pincode 411028
Nearby at
₹12,220
per sq ft, same sizes in Hadapsar
Available
3 BHK
151 left · 1,031–1,259 sq ft
Now due
Apr 2035
4 months later than first promised
A stock photograph, not Park Imperial Tower A. We have no picture of this site yet.
Plot Demarcation

Land & Survey Location

Official parcel address and geographic coordinates as declared to MahaRERA.

Jurisdiction Hadapsar · Haveli

Hadapsar, PMC, Pune, 411028

Street map of Hadapsar centred on the coordinate filed for Park Imperial Tower A, about 1.4 km across.
Streets within about 700 m of the pin the promoter filed. Map data © OpenStreetMap contributors.
Village Hadapsar
Taluka Haveli
Pincode 411028
Promoter Pin Coordinates 18.517043, 73.916971

The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.

Flat sizes on file

All 151 flats are filed unit by unit with the authority, the highest on floor 26. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.

Configuration Mix & Volume Proportional share of project density
151 Total Licenced Units
Dominant Typology • 82.8% of tower

3 BHK Residences

125 Available 125 registered total
Estimated Market Window ₹1.3 crore
Locality Benchmark ₹12,220 / sq ft
Carpet Variations as Filed Span: 1031 to 1057 sq ft
1031 sq ft 95.76 sq m 21 units
1036 sq ft 96.26 sq m 52 units
1046 sq ft 97.17 sq m 26 units
1057 sq ft 98.18 sq m 26 units
Govt ASR Base: ₹83.8 lakh – ₹89.6 lakh 125 of 125 available
Residential Typology • 17.2% of tower

Other Residences

26 Available 26 registered total
Estimated Market Window ₹1.5 crore
Locality Benchmark ₹12,220 / sq ft
Carpet Variations as Filed Span: 1259 sq ft
1259 sq ft 116.98 sq m 26 units
Govt ASR Base: ₹1 crore 26 of 26 available

Carpet Area vs. Loading Factor Arithmetic

How statutory carpet translates to standard Pune market quoted areas (+20% Built-up, +40% Super Built-up)

Unit Configuration Statutory RERA Carpet (Actual) Approx Built-up (+20%) Super Built-up (+40% Loading) Available Inventory
3 BHK 1031 – 1057 sq ft (95.76 – 98.18 sq m) ~1237 – 1268 sq ft ~1443 – 1480 sq ft 125 left of 125
Other 1259 sq ft (116.98 sq m) ~1511 sq ft ~1763 sq ft 26 left of 26
Units sold

0 / 151

Pre-launch / early phase

0% absorption rate

Visual area guide See what the filed sizes feel like 1 generic footprint scaled from the registered carpet areas.

What each size looks like

Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a flat that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that flat, and each flat to its size against the largest one drawn below.

3 BHK 125 flats · 125 available

1,036 sq ft carpet as drawn, from 1,031–1,057 sq ft filed in this configuration

Carpet, filed
1,036 sq ft
Built-up
about 1,243 sq ft
Super built-up
about 1,450 sq ft
Every room in this flat

Living and dining about 255 sq ft, Master bedroom about 170 sq ft, Second bedroom about 136 sq ft, Third bedroom about 110 sq ft, Kitchen about 102 sq ft, Bath about 59 sq ft, Balcony about 59 sq ft, Second bath about 51 sq ft, Passage about 51 sq ft, Third bath about 42 sq ft.

The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.

What flats like these cost nearby

No sale has been registered at Park Imperial Tower A yet. The promoter has filed no agreement values, so nothing below is this project's own price.

Independent Market Intelligence

Registered Agreement Rates in Hadapsar

Based on 1,895 government-stamped sale deeds registered for identical carpet bands across nearby developments.

3 BHK 1,031–1,057 sq ft
₹12,220 / sq ft

1,895 registered sale agreements across 33 nearby developments.

Estimated Unit Market Window ₹1.3 crore – ₹1.3 crore
Middle Half (IQR) ₹10,997 – ₹13,271 / sq ft
25th percentile: ₹10,997 75th percentile: ₹13,271

Each rate is what buyers contracted to pay for the same configuration in Hadapsar, over the carpet area on the same filing. Floor and facing move a rate, and a project new on the register can open above or below what its neighbours sold at two years ago, so the last column is arithmetic rather than a quote. See every rate registered in Hadapsar.

The government's valuation of the unsold flats

On sale here Carpet Valued at no less than
3 BHK 125 unsold 1,031–1,057 sq ft ₹83.8 lakh–₹89.6 lakh ₹8,194/sq ft
Not named 26 unsold 1,259 sq ft ₹1 crore ₹7,997/sq ft

This is the Annual Statement of Rates value the promoter filed against each unsold flat — the state's valuation, not an asking price and not a discount. Stamp duty is charged on whichever is higher, this or the agreement value, so nothing here can be registered below it. Read it as the floor under the price you will be quoted, which in most Pune localities sits well above it.

Filing Compliance

Timeline audit & delivery schedule

Possession milestones tracked directly against original MahaRERA declarations.

Filing State Revised (+4 months)
Original Baseline
Dec 2034
Declared at registration
Current Statutory Date
Due
Apr 2035
4 months later than filed

Revised delivery projection

The completion date has moved from December 2034 to April 2035, 4 months later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

SERVEY NO.131/2/3/5/8,HISSA NO.2A,2B,2D,2C,CTS NO.4683 is the plot this project is built on, as filed
Revenue village Hadapsar
TalukaHaveli
Street, as filed HADPSAR
Bounded north by By C.T.S. no. 4684/canal road/ C.T.S. 4711.
Bounded east by By C.T.S. nos. 4682, 4683.
Bounded south by By C.T.S. nos. 4681, 4685.
Bounded west by By D.P. road, C.T.S. nos. 4708 to 4711

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerIqoniq shelters llp
Registered office2413, 3rd Floor, Kumar Capital, East Street, Near Poolgate, Camp, Pune 411001

Professionals named on the filing

Architect Voussoirs CA/92/14618
Engineer Kumar Properties And Promoters Pvt Ltd NA
Chartered Accountant Supriya Abhijit Mundada 156545

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

20 April 2026 is when an advocate last certified the title to this land
Title report title.pdf 20 April 2026
Conveyance deed Deed of Conveyance 1-15.pdf 20 April 2026 2 older versions on file
Promoter's declaration, Form B FORM B AFFIDAVIT DECLARATION.pdf 18 April 2026
Annexure A declaration Annexure A Declaration cum Undertaking (2).pdf 20 April 2026

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberPR1261012600792
Promoter Iqoniq shelters llp
Project typeResidential / Group Housing · Building development
LocalityHadapsar — Haveli taluka, pincode 411028
Applied on21 April 2026
Registered on15 June 2026
Completion, as first filed31 December 2034
Due30 April 2035 4 months later
Units declared151
Units sold None sold yet, all 151 on the market
Complaints0 on record with MahaRERA
Certificate on file Original registration certificate, issued 15 June 2026
Application referenceACK18042600365
Current statusActive
Record last changed 15 June 2026 · 5 months ago

Nothing has sold yet. The promoter's quarterly progress report says none of the 151 flats are gone, and the unit-by-unit list they file separately says the same: all 151 still unsold. On a project this new that is normal rather than a warning, and it means every carpet area filed here is still available. Either way, this is only as current as the last change to the record, 15 June 2026.

Public Due Diligence

Common questions & statutory checks

Direct answers to questions buyers ask, verified strictly against the MahaRERA filing and registered deed records.

Verified Checks 7 Direct Answers
Is Park Imperial Tower A registered with MahaRERA?
Yes. It is registered as PR1261012600792, filed on 15 June 2026, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Park Imperial Tower A due to be handed over?
The promoter has told MahaRERA April 2035. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Park Imperial Tower A been delayed?
Yes. The first date filed was December 2034. It now stands at April 2035, 4 months later.
What does a flat in Park Imperial Tower A cost?
Nothing has been registered in this project yet, so it has no price of its own. Units the same size elsewhere in Hadapsar have registered at ₹12,220 per square foot of carpet — the neighbourhood, not this building.
How many flats are left in Park Imperial Tower A?
151 of 151 were still unsold at the promoter's last filing, in 3 BHK, from 1,031–1,259 sq ft of carpet.
Are there complaints against Park Imperial Tower A?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Park Imperial Tower A?
Iqoniq shelters llp, as the promoter named on the registration.

Verify Government Filings Yourself

This dossier restates public records as filed on 30 October 2026. The authority's own registry page for PR1261012600792 carries sanctioned layout drawings, escrow accounts, quarterly progress filings, and title documents.