RERA registered P52100051338 Active
Matoshri Prime
Alandi, Pune · Others by Shrimatoshri Infrabuild LLP
Official record Updated from the register 24 September 2026. Anything filed since then is not here yet.
In short
Matoshri Prime in Alandi is MahaRERA-registered (P52100051338) and still under construction, with possession filed for November 2026. Buyers have already registered 36 sales here at a median ₹7,537 per sq ft of carpet — not an asking price. About 71% of the 51 units are sold. Shrimatoshri Infrabuild LLP is the promoter.
- Sold here at
- ₹7,537
- per sq ft, 36 registered sales
- Available
- Office Space, Shops
- 5 left · 248–847 sq ft
- Now due
- Nov 2026
- 17 months later than first promised
Where this is
Alandi, PCMC, Pune, 412105
No coordinate was filed for this project, so this searches Maps by name and locality rather than dropping a pin we cannot vouch for.
Unit sizes on file
All 51 units are filed unit by unit with the authority, the highest on floor 7. Sizes are RERA carpet area — the floor you can actually walk on, not a built-up or saleable figure. The register holds them in square metres, so that figure is printed under each one: it is what you will see if you open the filing, and the square feet are our arithmetic on it.
1 BHK 24 units · none available
2 BHK 18 units · none available
Office Space 5 units · 3 available
Shops 4 units · 2 available
36 / 51
71% absorption rate
Visual area guide See what the filed sizes feel like 2 generic footprints scaled from the registered carpet areas.
What each size looks like
Generic layouts, not this project's plans. Only the carpet area is from the register — the rooms are the usual shares of a unit that size, and where the promoter actually put the kitchen or which way the balcony faces is not filed anywhere. Read them for scale, which is the part that is arithmetic on the register: each room is drawn to its share of the area filed for that unit, and each unit to its size against the largest one drawn below.
1 BHK 24 units · none available
356 sq ft carpet as drawn, from 356–512 sq ft filed in this configuration
- Carpet, filed
- 356 sq ft
- Built-up
- about 427 sq ft
- Super built-up
- about 498 sq ft
Every room in this unit
Living and dining about 134 sq ft, Master bedroom about 89 sq ft, Kitchen about 53 sq ft, Bath about 31 sq ft, Balcony about 31 sq ft, Passage about 18 sq ft.
2 BHK 18 units · none available
546 sq ft carpet as drawn, from 546–567 sq ft filed in this configuration
- Carpet, filed
- 546 sq ft
- Built-up
- about 655 sq ft
- Super built-up
- about 764 sq ft
Every room in this unit
Living and dining about 159 sq ft, Master bedroom about 106 sq ft, Second bedroom about 85 sq ft, Kitchen about 64 sq ft, Bath about 37 sq ft, Balcony about 37 sq ft, Second bath about 32 sq ft, Passage about 27 sq ft.
The built-up and super built-up figures are ours, not the promoter's: carpet plus 20% and plus 40%, which is the usual Pune loading. A promoter can load more, and the number they quote is the one to check against the agreement. Which of the three you are actually buying, and why the register only records one of them, is in our guide to carpet against super built-up area.
What buyers actually paid
| Range across those sales | ₹5,813 to ₹8,360 per sq ft |
|---|---|
| Sold and booked | 36 sold, 0 booked |
| Still available | 5 units, 248–847 sq ft |
A registered price is what a buyer contracted to pay, so it is the closest thing to a real number this market produces. It still is not a quote for you: these agreements were signed on different dates as the project progressed, floor and facing move the rate, and what a builder asks today may be higher or lower. Unsold units carry a government ready-reckoner valuation instead of a price, and that is a different thing, so it is not mixed into the figures above.
Timeline audit
Revised projection
The completion date has moved from June 2025 to November 2026, 17 months later, on the promoter's own revised filing.
Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.
RERA filing records
View allEvery figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.
| Field | As filed with MahaRERA |
|---|---|
| Registration number | P52100051338 |
| Promoter | Shrimatoshri Infrabuild LLP |
| Project type | Others · Building development |
| Locality | Alandi — Haveli taluka, pincode 412105 |
| Applied on | 23 May 2023 |
| Registered on | 08 June 2023 |
| Completion, as first filed | 30 June 2025 |
| Due | 30 November 2026 17 months later |
| Units declared | 51 |
| Units sold | 36 of 51 sold (71%), 15 still unsold |
| Complaints | 0 on record with MahaRERA |
| Certificate on file | Extension certificate, issued 04 September 2026 |
| Application reference | REA52100139435 |
| Current status | Active |
| Record last changed | 13 August 2026 · 42 days ago |
Where the sold count comes from, and whether it holds up. 36 of 51 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. But they file a second, separate thing with the same authority: the building unit by unit. That list accounts for all 51 units and reaches the same answer — 36 sold, every one with money recorded as received against a named unit, and 5 still unsold. Two filings, made separately, agreeing to the unit. That is not an audit, but it is a good deal harder to fudge than one round number. Either way, this is only as current as the last change to the record, 13 August 2026.
Common questions
- Is Matoshri Prime registered with MahaRERA?
- Yes. It is registered as P52100051338, filed on 08 June 2023, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
- When is Matoshri Prime due to be handed over?
- The promoter has told MahaRERA November 2026. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
- Has Matoshri Prime been delayed?
- Yes. The first date filed was June 2025. It now stands at November 2026, 17 months later.
- What did buyers actually pay in Matoshri Prime?
- A median of ₹7,537 per square foot of carpet, across 36 sale agreements registered in this project. That is what was paid and stamped, not what is being asked.
- How many units are left in Matoshri Prime?
- 5 of 51 were still unsold at the promoter's last filing, in Offices + shops, from 248–847 sq ft of carpet.
- Are there complaints against Matoshri Prime?
- None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
- Who is building Matoshri Prime?
- Shrimatoshri Infrabuild LLP, as the promoter named on the registration.
Check this yourself
This page restates one public record as we read it on 24 September 2026. The authority's own page for P52100051338 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.
MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.
Other projects in Alandi
Stock image
- Registered here
- ₹10,363
1 complaint
- Due
- Jun 2027
- Units
- 96
- Carpet
- 711–917
- Sold at
- ₹76.9 lakh
Stock image
- Registered here
- ₹947
- Due
- Jul 2028
- Units
- 96
- Carpet
- 7653–9870
- Sold at
- ₹74.8 lakh
Stock image
- Registered here
- ₹6,377
- On offer
- 1, 2, 3 BHK +2 more
- Due
- Apr 2028
- Units
- 134
- Carpet
- 137–1,541
- Sold at
- ₹40 lakh