RERA registered P52100054082 Active
Laxmi Paradise
Alandi Mhatobachi, Pune · Plotted by The Laxmi Empire
Official record Updated from the register 10 October 2026. Anything filed since then is not here yet.
In short
Laxmi Paradise in Alandi Mhatobachi is MahaRERA-registered (P52100054082) and still under construction, with possession filed for April 2029. No registered sale rate is on file for this project or its locality yet. About 7% of the 368 units are sold. 1 complaint sits on the filing. The Laxmi Empire is the promoter.
- Price
- Not filed
- no agreement or valuation on the register
- Available
- Not filed
- the promoter filed no unit list
- Now due
- Apr 2029
- 4 months later than first promised
Where this is
Alandi Mhatobachi, PMRDA, Pune, 412201
The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.
How much of this has sold
Carpet areas and the unit-by-unit breakdown are filed for most projects but are missing for this one, so the count below is all the register holds on what is being built here.
24 / 368
7% absorption rate
Timeline audit
Revised projection
The completion date has moved from December 2028 to April 2029, 4 months later, on the promoter's own revised filing.
Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.
The land itself
| Revenue village | AALANDI MHATOBA · shown on this site as Alandi Mhatobachi |
|---|---|
| Taluka | Haveli |
| Street, as filed | ALANDI MHATOBA |
| Bounded north by | MR SHIVARKAR PROPERTY |
| Bounded east by | SURBHAUGVASTI |
| Bounded south by | MR JAWALKAR PROPERTY |
| Bounded west by | ANIMAL FOREST |
Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.
"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.
Who is behind this project
Filed by the promoter with MahaRERA.
| Promoter on the register | The Laxmi Empire |
|---|---|
| Registered office | A 218, First Floor, Wing A, Mega Center, Pune Solapur Road, Mega Centre, Hadapsaar, Pune 411028 |
Professionals named on the filing
| Architect | Atit Admulwar CA/2008/41887 |
|---|---|
| Engineer | Mr Pritesh Shivaji Gaderao |
| Chartered Accountant | Amol Totala 160355 |
| Chartered Accountant | CA Yogesh Bhagat 132280 |
The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.
Complaints filed with MahaRERA
1 case against this project, 0 with an order on record. Complainants' names are published by the authority; we leave them out. Quote the case number to look one up.
| Case number | Filed | Outcome |
|---|---|---|
| CC12501767 | May 2025 | No order on record |
A complaint is not proof of wrongdoing, and a project with none is not necessarily well run — most buyers never file. What the pattern shows is whether disputes here reached the regulator and whether they were decided.
Title and ownership papers
| Title report 02 the legal title report.pdf | 26 November 2023 |
|---|---|
| Promoter's declaration, Form B 10 Declaration in FORM B N.pdf | 26 November 2023 |
No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.
So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.
RERA filing records
View allEvery figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.
| Field | As filed with MahaRERA |
|---|---|
| Registration number | P52100054082 |
| Promoter | The Laxmi Empire |
| Project type | Plotted · Plotted development |
| Locality | Alandi Mhatobachi — Haveli taluka, pincode 412201 |
| Applied on | 28 November 2023 |
| Registered on | 27 December 2023 |
| Completion, as first filed | 31 December 2028 |
| Due | 30 April 2029 4 months later |
| Units declared | 368 |
| Units sold | 24 of 368 sold (7%), 344 still unsold |
| Complaints | 1 on record with MahaRERA |
| Certificate on file | Original registration certificate, issued 27 December 2023 |
| Application reference | REA52100149945 |
| Current status | Active |
| Record last changed | 27 December 2023 · over 2 years ago 2 years untouched |
Where the sold count comes from, and whether it holds up. 24 of 368 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. There is no unit-by-unit filing on record for this project to check it against, so this is a single unverified number. Either way, this is only as current as the last change to the record, 27 December 2023.
MahaRERA has not recorded a change to this project's record in 2 years, while still listing it as under construction. That date moves on status changes and system updates as well as on anything the promoter files, so it is not proof the site is idle — but on a project still being sold, it is worth asking the promoter what has been filed since.
Common questions
- Is Laxmi Paradise registered with MahaRERA?
- Yes. It is registered as P52100054082, filed on 27 December 2023, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
- When is Laxmi Paradise due to be handed over?
- The promoter has told MahaRERA April 2029. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
- Has Laxmi Paradise been delayed?
- Yes. The first date filed was December 2028. It now stands at April 2029, 4 months later.
- Are there complaints against Laxmi Paradise?
- 1 case has been filed with MahaRERA against this project. A complaint is an allegation that has been lodged, not a finding against the promoter.
- Who is building Laxmi Paradise?
- The Laxmi Empire, as the promoter named on the registration.
Check this yourself
This page restates one public record as we read it on 10 October 2026. The authority's own page for P52100054082 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.
MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.
Other projects near Alandi Mhatobachi
Stock image
- Registered here
- ₹4,722
- On offer
- 1 BHK
- Due
- Dec 2026
- Units
- 55
- Carpet
- 118–286
- Sold at
- ₹13.5 lakh
Stock image
- Registered here
- ₹4,756
- On offer
- 1, 2, 3 BHK
- Due
- Dec 2029
- Units
- 209
- Carpet
- 424–782
- Sold at
- ₹30 lakh
Stock image
- Registered here
- ₹13,641
- On offer
- 3 BHK
1 complaint
- Due
- Jul 2028
- Units
- 14
- Carpet
- 1,028–1,125
- Sold at
- ₹1.5 crore