Sai Siddhi Promoters And Builders
4 RERA-registered projects in Pune, across 3 localities.
Under construction — 3 projects
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| Anshul Casa I-Building | Wakad | Jun 2026 | Mar 2027 | Under construction | 45% | 2 |
| Casalino Towers Phase 3 | Autade Handewadi | Oct 2026 | Feb 2027 | Under construction | 25% | 0 |
| Casalino Tower E Wing | Hadapsar | Sep 2027 | Sep 2027 | New launch | 0% | 0 |
Track record Delivered — 1 project Handed over; late deliveries are the best guide to the next deadline.
Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch.
| Project | Locality | Promised | Handed over | Late by | Sold | Complaints |
|---|---|---|---|---|---|---|
| Casalino Towers Phase Ii | Autade Handewadi | Dec 2023 | Dec 2023 | On time | 85% | 1 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Sai Siddhi Promoters And Builders's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.