8 RERA-registered projects in Pune, across 1 locality.

7under construction
1delivered
1past their date
3complaints
1 of the 7 projects this promoter still has under construction is past the completion date on their own filing.

Under construction — 7 projects

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Wellington C - D Charholi Sep 2026 Jan 2027 Under construction 98% 0
Wellington-E-H-J-K Charholi Dec 2027 Apr 2028 Under construction 97% 0
Wellington F-G Charholi Dec 2027 Apr 2028 Under construction 99% 0
Miami A6-A7-B1 Charholi Dec 2028 Apr 2029 Under construction 79% 1
Miami A4-A5 Charholi Dec 2029 Apr 2030 Under construction 57% 0
Miami-A1-A2-A3-B2 Charholi Dec 2029 Apr 2030 Under construction 0% 0
Wellington-L-M Charholi Sep 2026 Sep 2026 20 days over 98% 1
Advertisement
Track record Delivered — 1 project Handed over; late deliveries are the best guide to the next deadline.

Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch.

ProjectLocalityPromised Handed over Late by SoldComplaints
Soho Charholi Apr 2026 Apr 2026 On time 100% 1

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Pride Builders LLP's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.