Z Zomefy

Paras Multispace LLP

2 RERA-registered projects in Pune, across 1 locality.

1under construction
1delivered
0past their date
3complaints

Under construction — 1 project

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Rahul Downtown - Phase II Punawale Dec 2026 Aug 2027 Under construction 58% 1
Track record Delivered — 1 project Handed over; late deliveries are the best guide to the next deadline.

Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch. 1 of 1 arrived later than first promised, which is the closest thing on record to how this promoter treats a deadline.

ProjectLocalityPromised Handed over Late by SoldComplaints
Rahul Downtown - Phase I Punawale Apr 2025 Jul 2025 3 months 89% 2

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Paras Multispace LLP's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.