Z Zomefy

Mantra Zirconia Private Limited

4 RERA-registered projects in Pune, across 1 locality.

4under construction
0delivered
0past their date
0complaints
Nothing adverse on record. No project by this promoter is past its completion date, no registration has lapsed, and no complaints have been filed with MahaRERA.

Under construction — 4 projects

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Mantra Mesmer Phase 5 Mundhwa Dec 2026 Dec 2026 Under construction 97% 0
Mantra Mesmer Phase 4 Mundhwa Mar 2028 Mar 2028 Under construction 81% 0
Mantra Mesmer Phase 6 Mundhwa Dec 2027 Dec 2027 Under construction 82% 0
Mantra Mesmer Phase 7 Mundhwa Dec 2027 Dec 2027 Under construction 48% 0
Advertisement

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Mantra Zirconia Private Limited's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.