Kumar Beharay Properties LLP
5 RERA-registered projects in Pune, across 1 locality.
Under construction — 2 projects
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| Hillview Residency Building D | Kothrud | Jun 2027 | Oct 2027 | Under construction | 83% | 0 |
| Hillview Residency Building E | Kothrud | Jun 2027 | Oct 2027 | Under construction | 25% | 0 |
Track record Delivered — 3 projects Handed over; late deliveries are the best guide to the next deadline.
Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch. 1 of 3 arrived later than first promised, which is the closest thing on record to how this promoter treats a deadline.
| Project | Locality | Promised | Handed over | Late by | Sold | Complaints |
|---|---|---|---|---|---|---|
| Hillview Residency P Commercial | Kothrud | Sep 2024 | Sep 2025 | a year | — | 0 |
| Hillview Residency Building I | Kothrud | Dec 2026 | Dec 2026 | On time | 86% | 0 |
| Hillview Residency Building H | Kothrud | Dec 2026 | Dec 2026 | On time | 83% | 0 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Kumar Beharay Properties LLP's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.