5 RERA-registered projects in Pune, across 3 localities.

4under construction
1delivered
0past their date
0complaints
Nothing adverse on record. No project by this promoter is past its completion date, no registration has lapsed, and no complaints have been filed with MahaRERA.

Under construction — 4 projects

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Virtu Pimple Nilakh Jun 2026 Apr 2027 Under construction 48% 0
Tremont A, B And C Wings Mundhwa Dec 2028 Apr 2029 Under construction 0
Primarc Bavdhan Dec 2027 Dec 2027 Under construction 83% 0
Polaris Bavdhan Dec 2030 Dec 2030 Under construction 2% 0
Advertisement
Track record Delivered — 1 project Handed over; late deliveries are the best guide to the next deadline.

Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch.

ProjectLocalityPromised Handed over Late by SoldComplaints
Tremont D, E And F Wings Mundhwa Dec 2028 Dec 2028 On time 100% 0

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from The Excellaa's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.