Kohinoor Heights

Rajgurunagar, Pune · Residential / Group Housing by Abbas Ayub Ansari

Official record Updated from the register 21 September 2026. Anything filed since then is not here yet.

In short

Kohinoor Heights in Rajgurunagar is MahaRERA-registered (P52100054625) and still under construction, with possession filed for February 2027. No registered sale rate is on file for this project or its locality yet. The promoter has not filed a unit-by-unit inventory, so sizes and sold counts are not on this page. Abbas Ayub Ansari is the promoter.

Stock image, not a photograph of Kohinoor Heights Stock image
Where
Rajgurunagar
pincode 410505
Price
Not filed
no agreement or valuation on the register
Available
Not filed
the promoter filed no flat list
Now due
Feb 2027
4 months later than first promised
A stock photograph, not Kohinoor Heights. We have no picture of this site yet.

Where this is

Rajgurunagar, PMRDA, Pune, 410505

Village
Rajgurunagar (CT)
Taluka
Khed
Pincode
410505

No coordinate was filed for this project, so this searches Maps by name and locality rather than dropping a pin we cannot vouch for.

Unit list not filed

MahaRERA has this project on the register — name, promoter and the completion date above — but the promoter has not filed a flat-by-flat inventory. There is no sizes table and no sold count to show. The listing is here so you can still find it and check the site yourself.

Timeline audit

Original proposed Oct 2026
Current status Due Feb 2027

Revised projection

The completion date has moved from October 2026 to February 2027, 4 months later, on the promoter's own revised filing.

Under section 18 of the Real Estate (Regulation and Development) Act, a buyer whose possession is delayed beyond the date in the agreement may withdraw and claim a refund with interest, or stay and claim interest for every month of delay. That right attaches to the date in your agreement, not the date on this page.

Advertisement
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.

The land itself

G NO 123/1/8P is the plot this project is built on, as filed
Revenue village Rajgurunagar (CT) · shown on this site as Rajgurunagar
TalukaKhed
Street, as filed TINHEWADI ROAD
Bounded north by G NO 123 1 8 P
Bounded east by G NO 123
Bounded south by ROAD
Bounded west by G NO 123

Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.

"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.

Who is behind this project

Filed by the promoter with MahaRERA.

Promoter on the registerAbbas Ayub Ansari
Registered officeG No 123, Rajgurunagar, Tinhewadi Raod, Khed, Pune 410505

Professionals named on the filing

Architect swapnil potdar
Engineer Dev Jadhav
Chartered Accountant Sandhesh Jain

The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.

Title and ownership papers

5 December 2023 is when an advocate last certified the title to this land
Title report legal report.pdf 5 December 2023
Promoter's declaration, Form B 100 ₹ stump paper.pdf 5 December 2023

No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.

So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.

RERA filing records

View all

Every figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.

FieldAs filed with MahaRERA
Registration numberP52100054625
Promoter Abbas Ayub Ansari
Project typeResidential / Group Housing · Building development
LocalityRajgurunagar — Khed taluka, pincode 410505
Applied on05 December 2023
Registered on02 February 2024
Completion, as first filed01 October 2026
Due01 February 2027 4 months later
Units declaredNot stated — migrated from the pre-2017 register
Units sold Not stated
Complaints0 on record with MahaRERA
Certificate on file Original registration certificate, issued 02 February 2024
Application referenceREA52100150288
Current statusActive
Record last changed 02 February 2024 · over 2 years ago 2 years untouched

MahaRERA has not recorded a change to this project's record in 2 years, while still listing it as under construction. That date moves on status changes and system updates as well as on anything the promoter files, so it is not proof the site is idle — but on a project still being sold, it is worth asking the promoter what has been filed since.

Common questions

Is Kohinoor Heights registered with MahaRERA?
Yes. It is registered as P52100054625, filed on 02 February 2024, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
When is Kohinoor Heights due to be handed over?
The promoter has told MahaRERA February 2027. That is a declaration to the authority rather than a promise to a buyer; the date in your own agreement is the one that binds.
Has Kohinoor Heights been delayed?
Yes. The first date filed was October 2026. It now stands at February 2027, 4 months later.
Are there complaints against Kohinoor Heights?
None appear against this project in the register. That covers cases filed with MahaRERA, and nothing about disputes settled elsewhere or never filed.
Who is building Kohinoor Heights?
Abbas Ayub Ansari, as the promoter named on the registration.

Check this yourself

This page restates one public record as we read it on 21 September 2026. The authority's own page for P52100054625 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.

MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.

Other projects in Rajgurunagar

Stock image, not a photograph of Br 24 Stock image
Valued from
₹4,198
On offer
Hall +2 more
Under construction

Br 24

Anil Ramchandra Rakshe · Rajgurunagar

12 sold
Slipped 4 months
Due
Dec 2027
Units
16
Carpet
110–1,772
Typical unit
~₹5.4 lakh
P52100053879
Stock image, not a photograph of Classic Amrut Stock image
Registered here
₹4,635
On offer
1, 2 BHK + shops
Under construction

Classic Amrut

Classic Infra · Rajgurunagar

65 sold

1 complaint

Slipped 4 months
Due
Feb 2027
Units
71
Carpet
185–595
Sold at
₹21.6 lakh
P52100054029