Official record Updated from the register 04 October 2026. Anything filed since then is not here yet.
In short
Anantsrishti Phase I in Kanhe is MahaRERA-registered (P52100006401) and was handed over in September 2020. No registered sale rate is on file for this project or its locality yet. About 99% of the 123 units are sold. 10 complaints sit on the filing. Landscape Reality is the promoter.
- Price
- Not filed
- no agreement or valuation on the register
- Available
- Not filed
- the promoter filed no unit list
- Now due
- Sep 2020
- 1.5 years later than first promised
Where this is
Kanhe, Pune, 412106
The coordinates are the promoter's own, filed with MahaRERA. We have not checked them on the ground, and a filed pin is occasionally a few kilometres from the survey number on the same filing — if it does not look right, search by name.
How much of this has sold
Carpet areas and the unit-by-unit breakdown are filed for most projects but are missing for this one, so the count below is all the register holds on what is being built here.
122 / 123
99% absorption rate
Timeline audit
Revised projection
The completion date has moved from March 2019 to September 2020, 1.5 years later, on the promoter's own revised filing.
Buyers who took possession late here may still have had a claim under section 18 of the Real Estate (Regulation and Development) Act, which entitles them to interest for every month of delay beyond the date in their agreement. More usefully for anyone buying today, this is a record of how this promoter performed against their own filed date.
Deep due diligence Open the complete registry dossier Land, promoter, complaints, title papers, plans and the raw MahaRERA record.
The land itself
| Revenue village | Jambhul · shown on this site as Kanhe |
|---|---|
| Taluka | Mawal |
| Street, as filed | TAKVE ROAD |
| Bounded north by | GUT NO 405 |
| Bounded east by | GUT NO 400 AND 403 |
| Bounded south by | GUT NO 386 AND 380 |
| Bounded west by | 36 M WIDE RP ROAD |
Every promoter has to file the survey numbers of the land and what lies on each of its four sides. It is the driest thing on this page and the most useful if you are serious: the survey number is what the revenue record is keyed on, so it is what you quote to check the seven-twelve extract, and the boundaries are how you confirm on site that the plot you were shown is the plot that was registered.
"Street" is the register's own field name and promoters fill it with whatever they have — a road, a locality, sometimes the survey numbers again. It is printed as filed rather than tidied up.
Who is behind this project
Filed by the promoter with MahaRERA.
| Promoter on the register | Landscape Reality |
|---|---|
| Registered office | 101, Express Tower, Laxmi Road, Png Jewllers, Sadashiv Peth, Pune 411030 |
| Registered agents | 18 licensed agents may sell this project |
Professionals named on the filing
| Architect | Milind Pokharkar & Associates |
|---|---|
| Engineer | Sunil Mutalik |
The promoter appoints these, and MahaRERA requires the architect and engineer to certify progress before money can be drawn from the project account. A name that recurs across several of a builder's projects is normal; one that recurs across several lapsed ones is worth a question.
Complaints filed with MahaRERA
10 cases against this project, 10 with an order on record, filed between Dec 2018 and Jul 2021. Complainants' names are published by the authority; we leave them out. Quote the case number to look one up.
| Case number | Filed | Outcome |
|---|---|---|
| CC005000000095785 | Jul 2021 | Order passed Jul 2021 |
| CC005000000064839 | Nov 2020 | Order passed Nov 2020 |
| CC005000000064835 | Nov 2020 | Order passed Nov 2020 |
| CC005000000064836 | Nov 2020 | Order passed Nov 2020 |
| CC005000000064837 | Nov 2020 | Order passed Nov 2020 |
| CC005000000043797 | Dec 2019 | Order passed Dec 2019 |
| CC005000000033475 | Sep 2019 | Order passed Sep 2019 |
| CC005000000023124 | Jun 2019 | Order passed Jun 2019 |
| CC005000000022472 | Jan 2019 | Order passed Jan 2019 |
| CC005000000022150 | Dec 2018 | Order passed Dec 2018 |
A complaint is not proof of wrongdoing, and a project with none is not necessarily well run — most buyers never file. What the pattern shows is whether disputes here reached the regulator and whether they were decided.
Title and ownership papers
| Title report Anantsrishti Title Certificate.pdf | 29 July 2017 |
|---|---|
| Promoter's declaration, Form B B Form.pdf | 29 July 2017 |
No project reaches the register without an advocate's report on the title to its land, so a title report on file is the floor and not a distinction. What the date tells you is how recently somebody qualified looked. What none of it tells you is whether the title is clear: a report can record an objection, a pending suit or a missing consent and still be a perfectly valid filing, and nothing here reads the contents of the document.
So read it yourself before you pay a booking amount, and read the newest one. Every document above is on the authority's page for this project, under the filename shown — the link is in Check this yourself. What to look for in each one, and what having it on file does not prove, is set out in our guide to a project's title papers.
RERA filing records
View allEvery figure here is the authority's, not ours, as of the date at the top of this page. This is the raw record, reproduced without alteration.
| Field | As filed with MahaRERA |
|---|---|
| Registration number | P52100006401 |
| Promoter | Landscape Reality |
| Project type | Mixed · Building development |
| Locality | Kanhe — Mawal taluka, pincode 412106 |
| Applied on | 29 July 2017 |
| Registered on | 14 August 2017 |
| Completion, as first filed | 31 March 2019 |
| Handed over | 30 September 2020 1.5 years later |
| Units declared | 123 |
| Units sold | 122 of 123 sold (99%), 1 still unsold |
| Complaints | 10 on record with MahaRERA |
| Certificate on file | Original registration certificate, issued 10 April 2018 |
| Application reference | REA52100011887 |
| Current status | Completed |
| Record last changed | 13 June 2020 · over 6 years ago |
Where the sold count comes from, and whether it holds up. 122 of 123 is the promoter's own figure, from the quarterly progress report every registered project has to file. Nobody audits that. There is no unit-by-unit filing on record for this project to check it against, so this is a single unverified number. Either way, this is only as current as the last change to the record, 13 June 2020.
Common questions
- Is Anantsrishti Phase I registered with MahaRERA?
- Yes. It is registered as P52100006401, filed on 14 August 2017, and the registration is current. The authority's own record is the place to confirm that; this page restates it.
- Has Anantsrishti Phase I been handed over?
- Yes. The completion date on the register is September 2020.
- Has Anantsrishti Phase I been delayed?
- Yes. The first date filed was March 2019. It now stands at September 2020, 1.5 years later.
- Are there complaints against Anantsrishti Phase I?
- 10 cases have been filed with MahaRERA against this project. A complaint is an allegation that has been lodged, not a finding against the promoter.
- Who is building Anantsrishti Phase I?
- Landscape Reality, as the promoter named on the registration.
Check this yourself
This page restates one public record as we read it on 04 October 2026. The authority's own page for P52100006401 carries more that we do not republish: the registration certificate, every quarterly progress report, the sanctioned plans, parking allocation, the project bank account, and any declared litigation.
MahaRERA will ask you to type a CAPTCHA first. That is their gate, not a broken link — and it is the reason this page exists, because a register you have to solve a puzzle to read one project at a time is not one anybody comparing four projects will actually use.
Other projects in Kanhe
Stock image
- Done
- Nov 2019
- Units
- 114
- Carpet
- —
- Typical unit
- —
Stock image
- Done
- Jul 2023
- Units
- 21
- Carpet
- —
- Typical unit
- —
Stock image
- Done
- Jun 2025
- Units
- 57
- Carpet
- —
- Typical unit
- —