Shree Developers
5 RERA-registered projects in Pune, across 4 localities.
Under construction — 3 projects
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| Siddhi Plaza | Swargate | Dec 2023 | Dec 2026 | Under construction | 87% | 0 |
| Sonigara Quorra | Tathawade | Dec 2029 | Apr 2030 | Under construction | 35% | 0 |
| Pearl | Dhanori | Aug 2028 | Aug 2028 | Under construction | 72% | 0 |
Track record Delivered — 2 projects Handed over; late deliveries are the best guide to the next deadline.
Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch. 1 of 2 arrived later than first promised, which is the closest thing on record to how this promoter treats a deadline.
| Project | Locality | Promised | Handed over | Late by | Sold | Complaints |
|---|---|---|---|---|---|---|
| Sonigara Estilo | Tathawade | Dec 2024 | Dec 2026 | 2 years | 98% | 2 |
| Aditi Apartment | Dhankawadi | Jun 2026 | Jun 2026 | On time | — | 0 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Shree Developers's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.