Shakuntal Developers

2 RERA-registered projects in Pune, across 2 localities.

1under construction
0delivered
1past their date
0complaints
1 of the 1 project this promoter still has under construction is past the completion date on their own filing.

Under construction — 1 project

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Shakuntal Alentia Phase - I Chovisawadi May 2031 May 2031 New launch 0% 0
Registration ended Lapsed or de-registered — 1 project No longer covered by the protections that come with registration.

The registration period ended without an extension on record, or MahaRERA cancelled it. A lapsed registration does not mean the buildings are gone, but it does mean the project is no longer covered by the protections you registered for.

ProjectLocalityPromised Due Status SoldComplaints
Forestia Wing A Alandi Jun 2026 Oct 2026 7 days over 79% 0

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Shakuntal Developers's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.