Vishal Ashok Chugera
6 RERA-registered projects in Pune, across 2 localities.
Under construction — 5 projects
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| Nivaan Grandeur | Wagholi | May 2025 | Jun 2027 | Under construction | 83% | 0 |
| Nivaan Legacy | Wagholi | May 2027 | Sep 2027 | Under construction | 29% | 0 |
| Nivaan Sparsh Phase-1 | Theur | Jun 2027 | Oct 2027 | Under construction | 0% | 0 |
| Nivaan Water Edge Phase-II | Wagholi | Mar 2029 | Mar 2029 | Under construction | 0% | 0 |
| Nivaan Grandeur Phase-II | Wagholi | Mar 2031 | Mar 2031 | Under construction | 0% | 0 |
Track record Delivered — 1 project Handed over; late deliveries are the best guide to the next deadline.
Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch. 1 of 1 arrived later than first promised, which is the closest thing on record to how this promoter treats a deadline.
| Project | Locality | Promised | Handed over | Late by | Sold | Complaints |
|---|---|---|---|---|---|---|
| Fire Fly | Wagholi | Mar 2021 | Sep 2025 | 4.5 years | 93% | 0 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Vishal Ashok Chugera's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.