Vinayak Pandharinath Bhongale
2 RERA-registered projects in Pune, across 1 locality.
Under construction — 1 project
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| Gandharv Mithila Building A Wing E, F, G | Moshi | Dec 2026 | Apr 2027 | Under construction | — | 0 |
Registration ended Lapsed or de-registered — 1 project No longer covered by the protections that come with registration.
The registration period ended without an extension on record, or MahaRERA cancelled it. A lapsed registration does not mean the buildings are gone, but it does mean the project is no longer covered by the protections you registered for.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| Gandharv Nagari Building A3 Wing A, B | Moshi | Sep 2025 | Sep 2026 | 26 days over | 91% | 0 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Vinayak Pandharinath Bhongale's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.