Peninsula Land Limited
10 RERA-registered projects in Pune, across 2 localities.
Under construction — 5 projects
Live stock. These are the ones a booking amount today would go into.
| Project | Locality | Promised | Due | Status | Sold | Complaints |
|---|---|---|---|---|---|---|
| AshokVistas by Peninsula Land - Phase 2 | Ravet | Jun 2027 | Oct 2027 | Under construction | — | 0 |
| Peninsula Plaza | Gahunje | Mar 2028 | Jul 2028 | Under construction | 77% | 0 |
| AshokVistas by Peninsula Land Phase 1 | Gahunje | Dec 2026 | Apr 2027 | Under construction | — | 0 |
| Ashok Villas Imperial | Gahunje | Dec 2029 | Apr 2030 | Under construction | 0% | 0 |
| Ashok Villas Grande | Gahunje | Dec 2029 | Apr 2030 | Under construction | 0% | 0 |
Track record Delivered — 5 projects Handed over; late deliveries are the best guide to the next deadline.
Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch.
| Project | Locality | Promised | Handed over | Late by | Sold | Complaints |
|---|---|---|---|---|---|---|
| addressOne - Phase 1 | Gahunje | Dec 2022 | Dec 2022 | On time | 99% | 4 |
| Peninsula AshokVann Phase 1 | Gahunje | Jun 2023 | Jun 2023 | On time | 87% | 0 |
| Peninsula AshokVann Phase 2 | Gahunje | Apr 2024 | Apr 2024 | On time | 77% | 0 |
| Peninsula AshokVann Phase 3 | Gahunje | Jun 2024 | Jun 2024 | On time | 76% | 0 |
| Peninsula Centre Commercial Building Shopping Complex | Gahunje | Jul 2026 | Jul 2026 | On time | 100% | 0 |
How to read this
A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Peninsula Land Limited's own MahaRERA filings.
The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.