Z Zomefy

Four Pillars

3 RERA-registered projects in Pune, across 2 localities.

1under construction
2delivered
0past their date
1complaints

Under construction — 1 project

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
18 Aangan Maan Nov 2028 Nov 2028 Under construction 0% 1
Advertisement
Track record Delivered — 2 projects Handed over; late deliveries are the best guide to the next deadline.

Handed over and recorded as completed by MahaRERA, so ready-to-move or resale rather than a new launch. 1 of 2 arrived later than first promised, which is the closest thing on record to how this promoter treats a deadline.

ProjectLocalityPromised Handed over Late by SoldComplaints
Navkar Suchit Punawale Dec 2025 Jun 2026 5 months 92% 0
Navkar Anand Punawale Aug 2025 Aug 2025 On time 29% 0

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Four Pillars's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.