Evita Krisala Township LLP

3 RERA-registered projects in Pune, across 1 locality.

3under construction
0delivered
0past their date
5complaints

Under construction — 3 projects

Live stock. These are the ones a booking amount today would go into.

ProjectLocalityPromised Due Status SoldComplaints
Icon Darumbare May 2031 Sep 2031 Under construction 47% 0
Everland Darumbare Feb 2030 Jun 2030 Under construction 12% 1
Everlyn Darumbare Feb 2031 Jun 2031 Under construction 75% 4
Advertisement

How to read this

A promoter's past is the best available guide to their next project, and it is the one thing a brochure will never tell you. Every figure here is from Evita Krisala Township LLP's own MahaRERA filings.

The delivered table measures against the date first filed, so it shows whether this promoter tends to hit a deadline. The under-construction table measures against today, so it shows whether anything is running past its date right now. Read them together: a promoter who has delivered five projects late will probably deliver the sixth late too, and a slipped date is not necessarily misconduct — approvals and funding genuinely stall — but a pattern across several projects is worth asking about before you pay a booking amount.